  1. Home/
  2. Library/
  3. High Court Of Tripura/
  4. 2024/
  5. July

Sri Ratan Sarkar vs. the State of Tripura and Ors

Decided on 31 July 2024• Citation: WA/85/2024• High Court of Tripura
Download PDF

Read Judgment


                                             1  12                                  
                                         Page of                                    
                                 HIGH  COURT  OF TRIPURA                            
                                        AGARTALA                                    
                                      WA  No.85 of 2024                             
                Sri Ratan Sarkar, son of Late Rajendra Sarkar, resident of Ramnagar Road
                No.4, PO- Ramnagar, PS- West Agartala, Sub-Division- Sadar, District-
                West Tripura, PIN-799002, aged about 52 years.                      
                                                                 Appellant(s);      
                                                           ………                      
                                           Versus                                   
                1. The State of Tripura, represented by the Commissioner & Secretary,
                Public Works Department (Roads & Buildings), Government of Tripura, 
                having his office at New Secretariat Complex, Gorkhabasti, Agartala, PO-
                Kunjaban, PS- New Capital Complex, Sub-Division- Agartala, District-
                West Tripura                                                        
                2. The Commissioner & Secretary to the Public Works Department (Roads
                & Buildings), Government of Tripura, having his office at New Secretariat
                Complex, Gorkhabasti, Agartala, PO-Kunjaban, PS- New Capital Complex,
                Sub-Division- Agartala, District- West Tripura                      
                3. The Executive Engineer, Kumarghat Division PWD (R&B), Government 
                of Tripura, District- Unakoti Tripura.                              
                4. National Buildings Construction Corporation Limited (NBCC), a    
                Company, incorporated under the Companies Act, 1956, having its     
                registered office at NBCC Bhawan, Lodhi Road, New Delhi-110003,     
                represented by its General Manager, having his office at NBCC Bhawan,
                Lodhi Road, New Delhi-110003                                        
                5. The General Manager, having his office at NBCC Bhawan, Lodhi Road,
                New Delhi-110003                                                    
                6. The Senior General Manager (Engg), RBG Head- Tripura, National   
                Buildings Construction Corporation Limited, having his office at Jackson
                             rd                                                     
                Gate Building, 3 floor, Lenin Sarani, Agartala-799001, West Tripura 
                7. The Additional General Manager, National Buildings Construction  
                                                                     rd             
                Corporation Limited, having his office at Jackson Gate Building, 3 floor,
                Lenin Sarani, Agartala-799001, West Tripura.                        
                                                                Respondent(s).      
                                                          ………                       
                For Appellant(s)    : Mr. Somik Deb, Sr. Advocate,                  
                                     Mr. Pranabindu Chakraborty, Advocate.          
                For Respondent(s)   : Mr. Kohinoor N. Bhattacharyya, G.A.,          
                                     Ms. Kahina Reang, Advocate.                    

                                             2  12                                  
                                         Page of                                    
                                                  APARESH   KUMAR   SINGH           
                 HON’BLE  THE  CHIEF JUSTICE  MR.                                   
                                            TICE ARINDAM   LODH                     
                           HON’BLE  MR. JUS                                         
                                           Order                                    
                31/07/2024                                                          
                          Heard Mr. Somik Deb, learned senior counsel for the appellant
                and Mr. Kohinoor N. Bhattacharyya, learned Government Advocate for the
                respondents No.1 to 3.                                              
                2.        The writ petition was preferred for release of forfeited  
                performance guarantee amounting to Rs.12,80,147/- along with interest at
                the rate of 12% per annum from the date of invocation of bank guarantee till
                its actual realization in favour of the petitioner. The learned Writ Court vide
                impugned judgment dated 27.06.2024 dismissed the writ petition being
                WP(C) No.801/2023 as it was of the view that there are allegations and
                counter allegations made by the parties, but the record is not sufficiently
                placed before the Court by both the parties. The learned Writ Court observed
                that it would be appropriate if the matter is resolved by both the parties
                under Clause 24.1 of the contract agreement wherein it is stated that if any
                dispute or difference of any kind whatsoever arises in connection with or
                arising out of that contract of the execution of works or maintenance of the
                works, it would be referred for settlement to the competent authority. The
                learned Court, therefore, directed the parties to avail the remedies under
                Clause 24.1 of the contract as the Court could not go into the disputed
                questions of fact which were not placed on record. It was left open for the
                parties to place all the materials in support of their claim and counter claim
                before the competent authority under Clause 24.1.                   

                                             3  12                                  
                                         Page of                                    
                3.        The short factual canvas necessary to be referred to in order to
                appreciate the case of the parties are hereunder:                   
                          Petitioner was working under a work order dated 23.08.2010
                issued by the National Buildings Construction Corporation Limited [NBCC,
                for short] which is respondent No.4. The nature of the work was     
                           of Rural Roads under Pradhan Mantri Gram Sadak Yojana in 
                “Construction                                                       
                Jirania Block of West District of Tripura, Package No-IV (Ph-VII-R1-W)
                UG, DPR  No.TR-01-102 and routine maintenance of the work for five  
                                    ”                                               
                years. The work was to be executed within a period of eighteen months.
                Under the agreement, petitioner was required to maintain the work for the
                next five years. In the writ petition, his relief was confined to release of
                Rs.12,80,147/- which was in the nature of bank guarantee for security
                deposit made earlier. The bank guarantee was issued by the State Bank of
                India, Agartala Branch submitted in favour of the NBCC. Petitioner through
                his letter dated 04.06.2020 had sought release of Rs.19,36,302/- which were
                the amount withheld against his RA bills. He also submitted another letter to
                the General Manager (Engg.), NBCC Ltd. PMGSY works praying for      
                release of the security deposit of Rs.12,63,003/-. He further pursued the
                matter with the Assistant General Manager, State Bank of India, Agartala
                Branch through letter dated 13.10.2020. Petitioner contended that after
                completion of the five years maintenance period, there was no reason for
                withholding of the security deposit in the nature of bank guarantee.
                However, the Additional General Manager (Engg.) vide letter dated   
                03/05.03.2021 [Annexure-13] issued a show cause notice asking him to

                                             4  12                                  
                                         Page of                                    
                explain within seven days as to why action in accordance with the SBD
                Clause No.52.00 should not be taken against him as he had failed to 
                complete the work within the time specified in the contract agreement. It
                alleged that the progress of work was very dismal and poor and because of
                that, large number of public were deprived from the benefits of PMGSY
                scheme. Petitioner submitted his reply on 22.03.2021 [Annexure-14] inter
                alia stating that he had completed consecutive five years maintenance work
                and, therefore, was seeking release of the total amount of Rs.31,99,305/-.
                However, learned counsel for the petitioner submitted that no decision has
                been taken on his reply to the show cause notice. On the other hand, the
                Deputy General Manager (Fin.) issued letter No.NBCC/PMGSY/AGT/BG/   
                2021/1060 dated 28.05.2021 addressed to the Branch Manager, State Bank
                of India, Agartala Branch on the subject of release of original bank
                guarantee dated 11.10.2010 for Rs.12,80,147/-. The communication reads as
                under:                                                              
                         “Dear Sir,                                                 
                               Please refer to our letter no 1015 dt. 30.03.2021 wherein encashment
                         of BG of M/s Ratan Sarkar is issued. Now NBCC had withdrawn the said
                         letter and submitted original BG to Bank may release to Agency. Detail of BG
                         is already given below:-                                   
                                         BG No-0000220BG0000041                     
                                         Date of issue-17.10.2020                   
                                         Valid Upto-16.10.2021                      
                                         Amount-1280147/-”                          
                          Later the show cause issuing authority i.e. the Additional
                General Manager (Engg.) issued letter dated 18.06.2021 addressed to the
                Empowered Office, TRRDA, PWD (PMGSY), Agartala on the subject of    
                release of withheld amount of Link No.T04 (Jirania to Takarjala) to the

                                             5  12                                  
                                         Page of                                    
                Petitioner in connection with the said agreement. The said letter reads as
                under:                                                              
                         “Dear Sir,                                                 
                               The amount of Rs.19,36,302/- has been withheld from various RA
                         Bills of M/s Ratan Sarkar for the Link No.T04 Road name Jirania to Takarjala
                         under Jirania Block for pending ATR at construction period. Now there is no
                         pending ATR for construction period the above said road and the road has
                         been taken over by PWD (Jirania Division) as it is where is basis. The time
                         detail sheet of withheld amount is attached with this letter.
                               Hence, it is requested that kindly release the above withheld amount
                         to Agency as early as possible.                            
                                                         Yours Faithfully,          
                                                          Sd. Illegible             
                                                   Assistant General Manager (Engg.)”
                          It is not in dispute that Rs.19,36,302/- were withheld from the
                various RA bills of the petitioner, the computation of which also is indicated
                at Annexure-17, letter dated 28.05.2021 issued by the petitioner-contractor
                to the General Manager (Engg.), NBCC Ltd. The dispute surrounds around
                the release of security deposit in the nature of Bank Guarantee for 
                Rs.12,80,147/-.                                                     
                4.        Based on these contentions when the writ petition was filed,
                upon notice respondents No.4 to 7 appeared and filed their counter affidavit.
                Be it also indicated that though respondents No.4 to 7 are the NBCC and its
                officials i.e. the General Manager; the Senior General Manager (Engg.),
                RBG  Head-Tripura and the Additional General Manager, NBCC, West    
                Tripura but the author of the letter dated 28.05.2021 i.e. the Deputy General
                Manager (Fin.), who had intimated the Branch Manager, State Bank of 
                India, Agartala Branch of withdrawal of the encashment of bank guarantee
                of the petitioner vide letter No.1015 dated 30.03.2021, was not impleaded as
                a party. If the bank guarantee was already encashed through letter No.1015

                                             6  12                                  
                                         Page of                                    
                dated 30.03.2021, how could it be withdrawn after two months for being
                released to the agency? The respondents No.4 to 7 in their counter affidavit
                have supported the encashment of this Bank Guarantee as the petitioner did
                not fulfill the contractual obligations as per the agreement. It is stated that
                the physical condition of the road was terrible in respect of numbers of
                depressions and pot holes developed at several chain ages, as a result of
                which vehicular movement and pedestrians were suffering tremendously.
                This was repeatedly raised by public representatives and the local  
                inhabitants. As per the contractual terms, on completion of the construction
                work of the road, the same was to be handed over to the client after carrying
                out proper maintenance work for five consecutive years, but the petitioner
                failed to carry out the maintenance work as per provision embodied in the
                contract agreement. Even after several meetings and reminders from the
                respondents as well as TRRDA and notices served upon him, petitioner did
                not pay any heed to it. Therefore, the show cause notice was issued on
                03.03.2021. The show cause notice refers to several letters dated 09.09.2015,
                09.05.2016, 10.05.2016, 25.05.2016, 29.06.2016, 01.08.2016, 23.06.2017,
                19.06.2018 and 27.01.2020 issued to the petitioner in relation to the
                construction and maintenance of the upgradation road under the contract.
                Due to non-performance of regular maintenance work and considering the
                gravity of the road and regular public hurdles, PWD proposed NBCC to take
                over the                            vide letter dated 21.05.2021    
                        road on “As is where is basis”                              
                [Annexure-R/2]. As such, NBCC handed over the road to PWD on as is  
                                                                       “            
                where is basis . As per clauses of the standard bidding document for
                            ”                                                       

                                             7  12                                  
                                         Page of                                    
                PMGSY,  the respondents encashed the BG as a penalty owing to non-  
                performance of routine maintenance work by the contractor.          
                4.        Respondents have, while furnishing para-wise reply to the 
                averments made in the counter affidavit, made specific statements at para 15
                that on completion of the construction of the road on 31.03.2014, the road
                was to be handed over to the client in the year 2019 after carrying out proper
                maintenance work for five consecutive years. But the agency did not carry
                out the maintenance work as per the provisions of the contract. He did not
                pay any heed to the repeated notices and reminders served upon him and
                also several meetings held in that regard. Even after lapse of ample period of
                time, the road was kept without execution of periodic maintenance work.
                The matter was discussed with TRRDA at several occasions who were of the
                view that for any damage occurred due to non-execution of maintenance
                work as per the contract, the contractor would be held liable. On these
                averments, the respondents No.4 to 7 have made categorical statement that
                they were left with no other option but to encash the BG of the agency to the
                tune of Rs.12,80,147/- as per the terms of the contract agreement.  
                5.        Mr. Somik Deb, learned senior counsel for the appellant, in
                course of his submission has drawn the attention of this Court to Clause 24.1
                of the agreement which according to him is in the nature of a Dispute
                Redressal System. He has also drawn the attention of this Court to the
                decision of the Apex Court in the case of P. Dasaratharama Reddy    
                Complex v. Government of Karnataka and Another reported in (2014) 2 
                SCC 201 at paragraphs 10, 14, 27 & 42. He submits that the Dispute  

                                             8  12                                  
                                         Page of                                    
                Redressal System under Clause 24.1 is essentially a non-adjudicatory
                decision of the competent authority which is subject to right of the aggrieved
                party to seek remedy. As such, it is not an adjudication on the dispute raised
                by the appellant. Moreover, in view of Clause 25.1 of the contract, there will
                be no arbitration for settlement of any dispute between the parties in view of
                Clause 24 i.e. Dispute Redressal System. As such, no purpose would be
                served by invoking the forum of the competent authority/the Empowered
                Standing Committee in respect of the instant dispute under Clause 24.
                Learned senior counsel for the appellant further submits that since no
                decision on the show cause notice dated 03/05.03.2021 has been taken
                despite submission of his reply, and that the same Additional General
                Manager (Engg.), NBCC, Agartala has vide letter dated 18.06.2021 directed
                release of withheld amount of Rs.19,36,302/- from the running account bills
                of the petitioner as there is no pending Action Taken Report (ATR) for
                construction period of the said road, the withholding of amount of  
                Rs.12,80,147/- in the nature of a bank guarantee dated 11.10.2010 towards
                security deposit even after issuance of letter dated 28.05.2021 by the Deputy
                General Manager (Fin.) is without any basis and untenable. It is submitted
                that if there is no dispute left on the issue of satisfactory completion of the
                work and maintenance over a period of five years, the respondents cannot
                withhold the  security deposit of   Rs.12,80,147/- for which        
                petitioner/appellant herein had been compelled to move this Court. It is also
                submitted that the learned Writ Court however, despite noticing all these
                facts and circumstances, surprisingly refused to grant any relief and instead

                                             9  12                                  
                                         Page of                                    
                directed the parties to avail the remedies under Clause 24.1 which is in the
                nature of a non-adjudicatory decision by the Empowered Standing     
                Committee.                                                          
                6.        Mr. Deb, learned senior counsel for the appellant, has further
                relied upon at paragraph 82 of a decision rendered by the Apex Court in the
                case of M.P. Power Management Company Limited, Jabalpur v. Sky      
                Power Southeast Solar India Private Limited and Others reported in (2023)
                2 SCC 703 and submitted that there is no prohibition for the Writ Court in
                deciding disputed questions of fact particularly when the dispute surrounds
                demystifying of documents only. Since the claim of the petitioner was based
                on undisputed facts and interpretation of the construction of the terms of
                agreement such as Clause 24 & 25 which are non-adjudicatory decisions of
                the Empowered Standing Committee and which bars recourse to arbitration,
                the learned Writ Court ought not to have relegated the petitioner to the same
                forum instead of deciding the issue. As such, this Court in writ jurisdiction
                can grant relief to the appellant even in a contractual matter like this where
                there are no outstanding differences or dispute on the question of release of
                bank guarantee. Therefore, the impugned judgment may be set aside.  
                Respondents-NBCC may be directed to release the bank guarantee of   
                Rs.12,80,147/- in his favour.                                       
                7.        Mr. Kohinoor N. Bhattacharyya, learned Government Advocate
                appears for the respondents-State authorities. He submits that the entire
                claim of the appellant is directed against the NBCC. The NBCC has filed a

                                            10   12                                 
                                        Page   of                                   
                counter affidavit before the Writ Court where they have denied the claim on
                a number of grounds which also indicate existence of factual dispute
                between the parties.                                                
                8.        We have considered the submission of learned senior counsel
                for the appellant and learned Government Advocate for the respondents-
                State, and gone through the materials placed from the record. We have also
                perused the impugned judgment and taken note of the decisions cited on
                behalf of the appellant.                                            
                          The canvas of facts and documents which have been referred to
                in the foregoing part of this judgment creates an impression that for failure
                to maintain the road for a period of five years after its completion in the year
                2014, appellant has been served with a show cause notice on 03/05.03.2021
                giving references to at least nine such letters issued upon him from time to
                time. The show cause notice is related to poor performance and progress of
                the work. Appellant though has submitted his reply to the show cause notice
                on 22.03.2021, but it appears that the decision on his reply is either not taken
                or placed on record. On the other hand, the Additional General Manager
                (Engg.), the show cause issuing authority has, vide letter dated 18.06.2021,
                directed release of Rs.19,36,302/- from the running account bills of the
                                         rd        th        th                     
                petitioner which were against 3 RA bill, 4 RA bill, 5 RA bill and the
                final bill. However, this letter which has been relied upon on behalf of the
                appellant indicates release of only the withheld amount against running
                account bills and not release of the bank guarantee which is in the nature of a
                security deposit. The letter dated 28.05.2021 issued by the Deputy General

                                            11   12                                 
                                        Page   of                                   
                Manager (Fin.) addressed to the Branch Manager, SBI, Agartala Branch
                indicates that the bank guarantee submitted by the appellant for    
                Rs.12,80,147/- was already encashed by the NBCC vide letter No.1015 
                dated 30.03.2021. As such, withdrawal of the letter dated 30.03.2021 by
                letter dated 28.05.2021 issued by the Deputy General Manager (Fin.) after
                two months is difficult to understand and defies logic. A bank guarantee
                which already stood encashed two months back could not be restored by
                withdrawal of the letter of encashment.                             
                9.        The learned Writ Court while appreciating the case of the 
                parties, therefore, appears to be right in observing that there are allegations
                and counter allegations made by the parties but the record was not  
                sufficienty placed before the Court. In the absence of an undisputable state
                of affairs as to the admissibility of the security deposit amount of
                Rs.12,80,147/- in favour of the petitioner, no writ in the nature of Writ of
                Mandamus or direction could be issued for payment of the amount in favour
                of the petitioner. The counter affidavit of the respondents further makes it
                clear that the security deposit amount had been encashed due to poor
                performance of the maintenance work of the petitioner/appellant herein. As
                such, the arena of dispute in the facts and circumstances of the case
                discussed above is not undeniable.                                  
                10.       The Court in writ jurisdiction even in cases of claims arising
                under a contract may in the facts of a case exercise its discretionary
                jurisdiction to direct release of admissible amounts which are undisputed by

                                            12   12                                 
                                        Page   of                                   
                the parties. It may also enter into construction of salient terms and conditions
                of the contract if the factual arena does not suffer from any disputed
                questions. But when the claim involves issues which are not only disputed
                on the face of record but the pleadings and documents placed by the parties
                are insufficient to demystify the disputes surrounding those documents, it
                would indeed be unwise to accept the prayer of the appellant and direct
                payment of the amount of security deposit already encashed by the NBCC.
                The appellant may be right that Clause 24.1 provides for a non-adjudicatory
                decision by the Empowered Standing Committee, but in that case his remedy
                lies before the competent Court of civil jurisdiction since the issue involves
                determination on disputed questions of fact apart from construction of the
                terms of the agreement. Going by the ratio rendered by the Apex Court in
                the case of M.P. Power Management Company Limited (supra), we do not
                find that the relief prayed for by the appellant under writ jurisdiction can be
                granted in the facts and circumstances of the case. Therefore, the appeal
                being devoid of merit is dismissed.                                 
                11.       Pending application(s), if any, shall stand disposed of.  
                (ARINDAM  LODH),  J           (APARESH   KUMAR   SINGH), CJ         
                Pijush/                                                             
                MUNNA SAHA Digitally signed by MUNNA SAHA                           
                          Date: 2024.08.06 17:09:07 +05'30'