Skip to content
Order
  • Library
  • Features
  • About
  • Blog
  • Contact
Get started
Book a Demo

Order

At Order.law, we’re building India’s leading AI-powered legal research platform.Designed for solo lawyers, law firms, and corporate legal teams, Order helps you find relevant case law, analyze judgments, and draft with confidence faster and smarter.

Product

  • Features
  • Blog

Company

  • About
  • Contact

Legal

  • Privacy
  • Terms

Library

  • Acts
  • Judgments
© 2025 Order. All rights reserved.
  1. Home/
  2. Library/
  3. High Court Of Tripura/
  4. 2024/
  5. January

The State of Tripura and Anr vs. Sri Debashish Das Contractor

Decided on 31 January 2024• Citation: Arb.A./7/2022• High Court of Tripura
Download PDF

Read Judgment


                                            1  19                                   
                                         Page of                                    
                                    HIGH  COURT  OF TRIPURA                         
                                        AGARTALA                                    
                                   ARB.A. NO.07 OF 2022                             
               1.The State of Tripura,                                              
               represented by the Secretary-cum-Commissioner,                       
               Public Works Department(R&B),                                        
               New Secretariat Building,                                            
               PO Kunjaban, Agartala, West Tripura.                                 
               2. The State of Tripura,                                             
               represented by the Executive Engineer,                               
               PWD  (R&B), Kailashahar Division, Unakoti Tripura                    
                                                      .......Applicant-Appellant(s) 
                                          Versus                                    
               Sri Debashish Das, Contractor.                                       
               S/o Lt. Nirmal Bikash Das,                                           
               Joynagar, Middle Road,                                               
               Agartala-799002                                                      
               District:- West Tripura.                                             
                                                   ....... Respondent-contractor(s) 
               For the applicant-appellant(s) :   Mr. K. De, Addl. GA               
               For the respondent-contractor(s) : Mr. Somik Deb, Sr. Advocate,      
                                                  Mr. P. Chakraborty, Advocate      
               Date of hearing and delivery of                                      
               Judgment & Order              :    31-01-2024                        
               Whether fit for reporting     :    No                                
                            THE CHIEF  JUSTICE MR. APARESH  KUMAR  SINGH            
                    HON’BLE                                                         
                           HON’BLE  MR. JUSTICE ARINDAM  LODH                       
                                JUDGMENT    & ORDER(ORAL)                           
                    222                                                             
                         The issue falls under consideration in this appeal is in respect of
               the  Agreement  bearing No  01/SE(i)/EE/KLS/2014-2015(PBI) for       
               construction work of Central Jail, Kailashahar, Unokoti Tripura for an
               estimated value of Rs.10,94,94,941/- to be completed within the stipulated
               period of two years, the dispute arose between the parties which led to
               appointment of an arbitrator.                                        
               2.        Heard Mr. K. De, learned Addl. GA appearing for the applicant-
               appellants. Also heard Mr. Somik Deb, learned senior counsel assisted by
               Mr. P. Chakraborty, learned counsel for the respondent.              

                                            2  19                                   
                                         Page of                                    
               3.        This appeal filed under Section 37(1)(c) of Arbitration and
               Conciliation Act, 1996 read with Section 13(1A) of the Commercial Courts
               Act, 2015 is directed against the impugned judgment and order dated  
               16/03/2022 in Title Suit 04 (Arbitration) of 2020 along with Arbitral award
               passed by the learned Arbitral Tribunal dated 17/06/2020, in Arbitration Case
               No.ARB/SRB/2019(2) whereby and whereunder the learned District Judge,
               Unokoti District, by an order dated 16/03/2022 upheld the arbitral award
               passed by the sole Arbitrator and dismissed the application filed under
               Section 34 of the Arbitration and Conciliation Act.                  
               4.        The relevant factual details of the case of the parties as culled
               out from the pleadings on record are narrated hereunder:             
               4.1.       On  27/12/2013 the  Executive Engineer, PWD(R&B),         
               Kailashahar Division, Kailashahar, Unakoti Tripura published a Notice
               Inviting Tender(NIT) for execution of the instant work for an estimated
               amount of Rs.10,94,94,941 within a stipulated period of two years. The
               respondent-contractor dropped the tender for the said work and became the
               lowest tenderer at a tender value of Rs.11,71,04,839. Subsequently, the work
               was awarded to the respondent-contractor by issuing work order dated 
               06/06/2014, with a stipulated date of completion of two years. As per work
               order the stipulated date of commencement of the work was 20/06/2014 and
               the date of completion of the work was stipulated on 19/06/2016.     
               4.2.      Thereafter, an undated agreement bearing No 01/SE/11/EE/   
               KLSD/2014-2015 was entered between the contractor and the Executive  
               Engineer, who represented the State of Tripura, detailing the terms and
               conditions and price schedules etc.                                  

                                            3  19                                   
                                         Page of                                    
               4.3.      Accordingly, the respondent-contractor mobilized his working
               force and machinery but there was a delay in execution of the aforesaid
               agreement for 165 days i.e. from 02/12/2014 to 14/01/2016 at the instance of
               the appellants and as such the respondent-contractor had to remain idle for a
               considerable period of time as aforementioned. In addition, the work suffered
               further delay due to late supply/piece meal supply and changes in designs
               and drawings on several occasions and performing additional lead and lift in
               earth work due to geographical condition of site over which the respondent-
               contractor had no control, resulting in prolongation of the contract period and
               it became onerous for him to complete the work at the agreement rate due to
               abnormal rise in prices. The respondent-contractor proposed 30%      
               enhancement over the agreement rate to compensate price escalation and if
               the proposal so made was not acceptable, the contract would be closed. But
               the appellants on 31/01/2019 rescinded the contract instead of closing it.
               Moreover, the respondent-contractor also alleged that payment against
               additional lift and lead in the earth work as executed by the contractor has
               not been made, which cropped up as major dispute in between the claimant-
               contractor and the respondent-appellants.                            
               4.4.      On the other hand, the appellants alleged that the respondent-
               contractor deliberately suppressed the material fact and field realities with
               the intention of causing fraud and abuse of the process of arbitration.
               Moreover, the appellants by denying the contentions of the respondent-
               contractor alleged that the department had handed over the clear and 
               undisputed site to the respondent-contractor in time and performed reciprocal
               obligations as and when required. However, the department accepted the
               delay for 165 days as recorded in hindrance register and agreed on principle

                                            4  19                                   
                                         Page of                                    
               to give extension for this delay without any levy of compensation as 
               envisaged in the L.D. Clause. Further, the appellants denied the price
               escalation as demanded by the respondent-contractor as it was not as per
               provision of the agreement. The appellants also alleged that the contractor
               was provided enough opportunities to execute the work by extending time
               and carrying out reciprocal obligations, but the respondent-contractor
               suspended the work from time to time denying the instructions of the 
               appellants and ultimately stopped the work in the month of March, 2017 and
               remained adamant to enhance the rate @30% over the agreement rate for
               executing further work. But when all efforts to re-start the work failed, the
               appellants rescinded the contract under the provisions of the agreement, after
               serving show cause notice to the respondent-contractor.              
               4.5.      The respondent-contractor objected to the final action taken by
               the appellants depicting various grounds. As regards, payment against
               additional lead and lift in the execution of earth work as claimed by
               respondent-contractor, it is the stand of the appellants that the amount
               claimed by the respondent-contractor is not entertainable and whatever
               amount is payable on account of extra/additional lead and lift has been taken
               into consideration under extra item Nos.11 and 14(in total Rs.2,92,334/-), as
                        th                                                          
               shown in 7 RA and final bill, the balance outstanding payment of which is
               yet to be paid.                                                      
               4.6.      As a result, disputes arose between the parties, which resulted
               into appointment of a  sole arbitrator on 28/5/2019 vide order       
               no.7(17)/CE/PWD (Building).                                          

                                            5  19                                   
                                         Page of                                    
               4.7.       Considering the controversies transpired from the respective
               statement of claims and defense and the documents filed by the parties, the
               learned Arbitrator framed the following issues:                      
                          1. Whether the arbitration case is maintainable in its present form.
                         “                                                          
                         2. Whether the claimant is entitled to get the balance outstanding payment
                         against the work executed upto 3-1-2017, but not measured? Rs
                         50,00,000/-                                                
                         3. Whether the claimant is entitled to get the balance outstanding payment
                         against the extra/deviated item for additional lift, but not measured? Rs 1,
                         31.44,169/-                                                
                         4. Whether the claimant is entitled to get the balance outstanding payment
                         against the work executed as extra item for additional lead, but not
                         measured? -Rs 1,03,95,679/-                                
                         5. Whether the claimant is entitled to get the balance outstanding payment
                         against the work executed and measured, but not paid? Rs 28,01,334/-
                         6. Whether the claimant is entitled to get refund of security deposit?
                         Rs.14,05,000/                                              
                         6(a)- Whether the claimant is entitled to get refund of earnest money
                         amounting to Rs.10,95,000 ?                                
                         7. Whether the claimant is entitled to get outstanding payment against
                                           th                                       
                         price escalation bill upto 6 R.A. BILL?-Rs 1,37,99,630/-   
                         7(a)-Whether the claimant is entitled to get loss incurred due to overhead
                         expenses amounting to Rs12,45,000?                         
                         7(b)-Whether the claimant is entitled to get loss on the cost of materials
                         brought to site amounting to Rs20,00,000?                  
                         8. Whether the rescission of contract by the respondent is lawful or not?
                         9. Whether the claimant is entitled to get loss of expected profit @ 15% on
                         the balance work remaining unexecuted?- Rs 34, 24,048/-    
                         10. Whether the respondent Is entitled to get the difference of cost
                         amounting to Rs 1,10,50, 639/- for completing the unexecuted work left by
                         the claimant?                                              
                         11. Whether the claimant and/or respondent is/are entitled to get interest
                         on dues to be paid to the claimant or respondent as per provisions of the
                         Arbitration and Conciliation Act, 1996 as amended? - As would be decided
                         by Arbitrator                                              
                         12. Whether the claimant or respondent is entitled to any Cost? -As would
                         be decided by Arbitrator.                                  
                                          ”                                         

                                            6  19                                   
                                         Page of                                    
               4.8.      On going through the documentary evidence furnished by both
               the parties with their respective statement of claims and defense and having
               heard the learned counsel of the parties, the learned Arbitrator by the
               impugned order dated 18.04.2017 declared the award in the following  
               manner:                                                              
                         “Summary of award                                          
                         Issue No-1-Whether the claim petition of the claimant contractor is
                         maintainable?                                              
                         It is declared by the sole arbitrator that claim petition of the claimant
                         contractor is maintainable for the reasons as discussed under issue No-1
                         Issue No-2- Whether the claimant is entitled to balance outstanding
                         payment against work executed upto 3-1-2017, but not measured?
                         - Rs.50,00,000/-                                           
                         This claim under issue-2 has not been established and hence NIL Award.
                         Issue-3.Whether the claimant is entitled to get the balance outstanding
                         payment against the extra/deviated item for additional lift, but not
                         measured? Rs 1,31,44,169/-                                 
                                           AND                                      
                         Issue-4.Whether the claimant is entitled to get the balance outstanding
                         payment against the work executed as extra item for additional lead, but
                         not measured? -Rs 1,03,95,679/-                            
                         Both the issues are discussed together. The claims under these issues are
                         not established and hence NIL award.                       
                         Claim No-5.- Whether the claimant is entitled to get outstanding payment
                         against executed work measured but not paid ?-28,01,334    
                         The issue has been established. The tribunal awards a sum of Rs.39,66,805
                         against CLAIM No-5. The awarded amount is subjected to statutory
                         deduction, if not already made. The amount after deduction, if any, shall
                         carry simple interest @ 5% from the commencement of arbitration up to
                         the date of making award and whereafter it shall carry interest @ 7% till
                         realisation.                                               
                         6. Whether the claimant is entitled to get refund of security deposit? Rs.
                         14,05,000/-                                                
                         6(a)- Whether the claimant is entitled to get refund of earnest money
                         amounting to 10,95,000?                                    
                         The claims under these issues 6 and 6(a) are established. The security
                         deposit and earnest money claimed are released. The released security

                                            7  19                                   
                                         Page of                                    
                         deposit and earnest money, will however carry no interest, if paid within
                         forty days; otherwise it will carry simple interest @ 5% per annum after
                         forty days from the date of publication of award up to the date of
                         realisation.                                               
                         7.Whether the claimant is entitled to get outstanding payment against price
                         escalation bill upto 6 R.A. BILL?-Rs.1,37,99,630/- as revised to
                                       th                                           
                         Rs.1,44,64,88 up to 7 R.A, BILL.                           
                         The claim under the issue is partially established, Awarded a sum of
                         Rs.1,07,73,166 against claim under this issue, with interest @ 5% p.a.
                         from the commencement of arbitration up to the date of making award and
                         thereafter it shall carry interest @ 7% till realisation.  
                         7(a)-Whether the claimant is entitled to get loss incurred due to overhead
                         expenses amounting to Rs12,45,000?                         
                         The claim under this issue is partially established. The tribunal awards a
                         sum of Rs. 3.32,000/--                                     
                         The awarded sum shall carry interest @ 5% p.a. from the commencement
                         of arbitration up to the date of making award and thereafter it shall carry
                         interest @ 7% till realisation.                            
                         Issue-7(b)-Whether the claimant is entitled to get loss on the cost of
                         materials brought to site amounting to Rs20,00,000?        
                         The claims under the issue 7(b) not established. Nil award.
                         -Issue No-8"Whether the rescission of contract by the respondent is lawful
                         or not.                                                    
                         The arbitral declares that the rescission of contract by the respondent is
                         not legally valid. Reasons are stated while discussing the issue.
                         Issue No-9. Whether the claimant is entitled to get loss of expected profit
                         @ 15% on the balance work remaining unexecuted? Rs 34, 24,048/- as
                         revised to Rs55,25,319                                     
                         The claim under this issue is partially established. A sum of Rs 22,98,587-
                         is awarded under this issue. The awarded sum shall carry interest @ 5%
                         p.a. from the commencement of arbitration up to the date of making award
                         and thereafter it shall carry interest @ 7% till realisation.
                         Issue No-10.Whether the respondent is entitled to get the difference of cost
                         amounting to Rs 1,10,50, 639/- for completing the unexecuted work left by
                         the claimant ?                                             
                         This is a counter-claim from respondent. The claim is not established. Nil
                         award.                                                     
                                             imant and/or respondent is/are entitled to get
                         Сlaіт No.11. Whether the cla                               
                         interest on dues to be paid to the claimant or respondent as per provisions

                                            8  19                                   
                                         Page of                                    
                         of the Arbitration and Conciliation. Act, 1996 as amended? - As would be
                         decided by Arbitrator                                      
                         The tribunal has awarded interest separately, where applicable, while
                         discussing the issues. There is no need to discuss the issues under this
                         issue.                                                     
                         12. Whether the claimant or respondent is entitled to any Cost? -As would
                         be decided by the Arbitrator                               
                         Awarded a sum of Rs.5,74,230 to the claimant with direction that 35% of
                         the cost so awarded shall have to be paid to the respondent with interest
                         where applicable                                           
                                    .”                                              
               4.9.      Being aggrieved by the award dated 17/06/2020, the appellants
               filed a petition before the Court of learned District Judge, Unokoti District,
               Kailashahar under Section 34 of the Arbitration and Conciliation Act, 1996
               for setting aside the arbitral award passed by the learned Arbitrator in
               Arbitration Proceeding No.02 ARB/SRB of 2019 which was registered as 
               Title Suit 04 (ARBITRATION) of 2020. The learned District Judge by an
               order dated 16.03.2022 upheld the arbitral award passed by the learned
               Arbitrator and rejected the petition filed by the appellants. Hence, the instant
               Appeal.                                                              
               5.        Mr. K De, learned Addl. G.A. appearing for the appellants  
               submitted that learned District Judge, Unokoti Judicial District failed to
               appreciate the arbitral award arrived at by the learned Sole Arbitrator.
               Moreover, the learned Court below as well as the learned Sole Arbitrator
               have failed to consider that none of the 13 claims as submitted by the
               Contractor-Respondent is covered by the terms and conditions of the  
               contract. Further, the learned District Judge as well as the learned Sole
               Arbitrator have failed to consider that the claimant-respondent is not at all
               entitled to get payment as per issue No. 2 as the payment relating to issue No.
               2 has already been paid to the Contractor-Respondent. Also, they failed to

                                            9  19                                   
                                         Page of                                    
               consider Issue No. 3 that the Contractor-Respondent is not entitled to get any
               amount as the said claim for lift had already been measured and      
                               th                                                   
               Rs.1,71,906/- upto 7 RA bill and final bill had already been paid to the
               Contractor Respondent. The learned District Judge, Unakoti Judicial District
               as well as the Sole Arbitrator have failed to consider that the interest of 7%
               so preferred for any delay beyond the time frame is not entertainable as there
               is no provision of contract exists in the agreement in this regard.  
               5.1.      Mr. De, learned Addl. GA further submitted that according to
               clause 44 of the agreement price escalation clause as inserted in the
               agreement will not be applicable in this case and as such the contractor
               respondent is not entitled to any amount as escalation of price. As a result,
               state had suffered irreparable loss due to suspension of work by the 
               respondent contractor. Moreover, the Respondent Contractor was never 
               forced to dump the materials at the work site rather, it was the duty of the
               contractor concerned to procure materials according to requirement of the
               work.                                                                
               6.        In the instant appeal, the appellants have inter alia made the
               following prayers:                                                   
                         “(i) Admit this application;                               
                         (ii) Issue notice upon the respondent;                     
                         (iii) Call for the LC records;                             
                         (iv) After hearing the parties, set aside the judgment and order dated
                         16/03/2022 passed in Title Suit 04 (Arbitration) of 2020 by the Ld District
                         Judge, Unakoti District, Kailashahar along with arbitral Award passed by
                         the Ld. Arbitral Tribunal on 17/06/2020 in Arbitration Case No.
                         ARB/SRB/2019(2);                                           
                         (v) Any other order/order(s) may pass as Your Lordship may deem fit and
                         proper.                                                    
                                                  AND                               
                         For this act of kindness the Appellant as in duty bound shall ever pray.”

                                            10  19                                  
                                         Page of                                    
               7.        On  the other hand, Mr. Somik Deb, learned senior counsel  
               appearing for the respondent-contractor submitted that the claimant  
               respondent ( c    for short) had raised his claims under various Heads,
                         ‘ laimant’                                                 
               and the learned Arbitrator, by the impugned Award dated 17.06.2020 had
               partly allowed the claims of the claimant. According to learned senior
               counsel, ground Nos. I to IV are too vague, to inspire any confidence, and
               therefore, do not merit any consideration. According to learned senior
               counsel, ground No.V cannot be sustained inasmuch as the same relates to
               the findings, recorded by the learned Sole Arbitrator with reference to issue
               No.2 of the Claims, raised by the Claimant. The said Issue has been decided
               against the Claimant, and therefore, the appellants cannot have any justifiable
               reason to feel aggrieved. Moreover, Ground No.VI cannot be sustained 
               inasmuch as the same relates to the findings, returned by the learned Sole
               Arbitrator with reference to Issue No.II raised by the Claimant as the said
               Issue has also been decided, against the claimant, and hence, the appellants
               cannot be treated to be as aggrieved parties against the said finding. The next
               Ground namely, Ground No. VII appertains to grant of Interest, awarded by
               the Learned Sole Arbitrator, in favour of the claimant. In this context, it is
               submitted that the mandate, contained in the two Clauses (a & b) of Section
               31(7) of the Act assumes paramount significance.                     
               7.1.      Moreover, Mr. S. Deb, learned senior counsel appearing for the
               respondent-contractor submitted that Section 31(7)(a) of the Act relates to
               the award of Interest by the Arbitrator from the date of accrual of the cause
               of action to the date of Award. Accordingly, Section 31(7)(a) relates to
               Interest pendente lite. The expression "unless otherwise aggrieved by the
               parties', 'sum' & 'award is made Interest', assumes paramount significance.

                                            11  19                                  
                                         Page of                                    
               7.2.      Learned senior counsel has placed reliance upon the following
               judgments of the Apex Court:                                         
                 i)                                                                 
                      Hyder Consulting (UK) Ltd. v. State of Orissa, (2015) 2 SCC   
                      189, Paragraph nos. 2, 7, 13, 26, 28 & 29                     
                 ii)  Morgan  Securities & Credits (P) Ltd. v. Videocon Industries  
                      Ltd., (2023) 1 SCC 602, paragraphs 1, 4 to 6, 13, 14, 16, 17, 20
                      to 25, 27 & 28,                                               
               7.3.      Mr. Deb, learned senior counsel for the respondent-contractor
               submitted that Arbitrator would be well within his limits & jurisdiction to
               award Interest, at such rate, as he may deem reasonable, on the whole/part of
               the money, payable for the whole/part of the period, between the date of
               accrual of cause of action to the date of making/passing of the Award. Thus,
               the Arbitrator would be well within his limits & jurisdiction to award
               Interest, at such rate, as he may deem reasonable.                   
               7.4.      Furthermore, Mr. Deb, learned senior counsel for the       
               respondent-contractor submitted that, from a conspectus of the above two
               judicial pronouncements, it remains beyond the cavil of any dispute that the
               Arbitrator was well within his jurisdiction, in awarding Interest, in favour of
               the Claimant, and therefore, the judicial intervention, as sought for, by the
               appellants, vide Ground No. VII & XI of the Memorandum of Appeal, does
               not merit any consideration.                                         
               7.5.      While discussing Ground No.VIII, Mr. Deb, learned senior   
               counsel for the respondent-contractor submitted that the Award of the
               Arbitrator under Clause 44 of the agreement is sustainable.          
               7.6.      Moreover, learned senior counsel vehemently argued that the
               Work Order was issued, in favour of the Claimant on 06.06.2014, with a
               stipulation that the parties to the contract should execute the Agreement

                                            12  19                                  
                                         Page of                                    
               within 15 days, from the date of issuance of the Work Order, i.e., on or
               within 21.06.2014. Accordingly, the agreement was executed between the
               Claimant & the employer and the scheduled date of commencement of the
               work stipulated thereunder was 20.06.2014, with a stipulation that the work
               had to be concluded within two years therefrom. It is also an admitted fact
               that the execution of the work was hindered, on account of delay of 165 days,
               solely attributable to the employer. The said act had also been noted in the
               Hindrance Register, which has been adverted to by the learned Sole   
               Arbitrator in his Award.                                             
               7.7.      Learned senior counsel has referred Clause 44 of the Agreement
               which provides for Price Adjustment. Under Clause 44 of the Agreement, the
               Claimant was/is entitled to price escalation inasmuch as the said Clause is
               couched in a negative language, thereby embracing twin conditions, namely:-
                    i) value of the work to be Rs.1.00 crore and above, and         
                    ii) the period for completion of the work is 24 months or less thereto.
               7.8.      For invocation of the negative stipulation, contained in Clause
               44 of the Agreement, both the conditions mentioned therein, are mutually
               inclusive Clauses, and hence, are not applicable in the instant case as
               submitted by learned senior counsel, Mr. Deb for the respondent-contractor.
               Moreover under Clause 44.1 of the Agreement, which is couched in a   
               positive language mandates that Price Adjustment would be admissible to a
               contractor, where the estimated price of the work is more than Rs.1.00 crore,
               and having a completion period of more than 24 months.               
               7.9.      Moreover learned senior counsel appearing on behalf of the 
               respondent-contractor submitted that it is an admitted position that the value
               of the contract in question is more than Rs.2.00 crores, and it was completed

                                            13  19                                  
                                         Page of                                    
               within a period of more than 24 months. The second sentence of Clause 44.1
               of the Agreement amplifies the above position, by mandating that Price
               Adjustment would be applicable, within the original contract period, as also
               in the extended time for  completion, due to the fault of the        
               respondent/employer.                                                 
               7.10.     Clause 44 of the Agreement employs the expression 'stipulated
               time for completion', but Clause 44.1 of the Agreement employs the   
               expression 'having completio                      . The second       
                                      n period of more than 24 months’              
               sentence of Clause 44.1 of the Agreement i.e. This should be applicable
                                                     “                              
               within the original contract period extended period owing to departmental
                     leads to a conclusion that Clauses 44 & 44.1 of the Agreement  
               delay”                                                               
               operates in two different fields, and one is no substitute for the other, and
               hence, the said claim of the claimant under Issue No. ii is sustainable, under
               Clause 44.1 of the Agreement.                                        
               7.11.     Further, learned senior counsel appearing on behalf of the 
               respondent-contractor submitted that both under Clause 44 & Clause 44.1 of
               the Agreement, the Claimant was/is entitled to Price Escalation/enhanced
               rate for execution of the work, which had been asserted by him.      
               7.12.     Moreover, it is contended by the learned senior counsel    
               appearing on behalf of the respondent-contractor that a recital contained in
               the Agreement to the effect that time is the essence of the contract, is by
               itself, not conclusive of the fact that the time is the essence thereof, and
               whether time is the essence of the contract is a question of intention of the
               parties to the contract, to be gathered from the Terms of the contract. Further,
               it is submitted that when a contract provided for imposition of penalty and
               grant of extension of time, and the contractee grants extension of time,

                                            14  19                                  
                                         Page of                                    
               without imposing any penalty therefore, then in such circumstances, it cannot
               be inferred that the time was the essence of such a contract.        
               7.13.     In support of his submission, learned Counsel for the      
               respondent-contractor has placed reliance upon the following judgments of
               the Apex Court (i) Hyderabad Municipal Corpn. v. M. Krishnaswami     
               Mudaliar, (1985) 2 SCC 9, (ii) Asian Techs Ltd. v. Union of India, (2009)
               10 SCC 354 (iii) Asian Techs Ltd. v. Union of India, (2009) 10 SCC 354,
               and argued that since, the execution of the work was hindered for 165 days,
               for reasons attributable to the employer, applying the mandate, contained in
               Clause 44.1 of the Agreement, it may be concluded that the said period of the
               execution of the work was two years + 165 days. Since, the period of 
               execution of the work actually got extended beyond two years, the negative
               stipulation, contained in clause 44 of the Agreement would not come into
               play.                                                                
               7.14.     Moreover, learned senior counsel appearing on behalf of the
               respondent-contractor submitted that an arbitrator is the best interpreter of
               the Clauses of the Agreement, and any erroneous interpretation of a Clause
               of an Agreement cannot constitute a valid basis for challenge, either under
               Section 34(ii) read with the Explanation appended thereto, or Section 34(2A)
               of the Act. It is submitted that the Proviso, appended to the substantive part
               of Section 34(ii) of the Act amplifies the above two contention. In view of
               the same, since, a challenge on the aforesaid premise is not maintainable,
               under Section 34 of the Act, as a corollary thereof, it logically follows
               therefrom that a challenge under the said premise, is equally not    
               maintainable, under Section 37(1)(c) of the Act.                     

                                            15  19                                  
                                         Page of                                    
               7.15.     In this context, learned senior counsel appearing on behalf of the
               respondent-contractor referred following judicial pronouncements:-   
                 i)   Associate Builders v. DDA, (2015) 3 SCC 49, paragraph nos.15  
                      to 19, 27 to 30, 35, 36, 40, 42.1 & 42.2;                     
                 ii)  Ssangyong Engg. & Construction Co. Ltd. v. NHAI, (2019) 15    
                      SCC  131, paragraph nos. 20, 26, 34 to 44, 67 & 68; and       
                 iii)  Delhi Airport Metro Express (P) Ltd. v. DMRC, (2022) 1 SCC   
                      131 Paragraph nos. 22, 24, 26, 28, 29 to 31, 37 to 43, 48 to 52.
               8.        We  have considered the rival submissions of learned counsel
               appearing for the parties and gone through the relevant materials placed on
               record. We have also gone through the award returned by the learned  
               Arbitrator as well as the judgment and order passed by learned District
               Commercial Court by which the arbitral award passed by the learned   
               Arbitrator has been upheld.                                          
               8.1.      The scope of interference in an appeal under Section 37 of the
               Act of 1996 has been delineated in the decisions rendered by the Apex Court.
               We are inclined to refer to the latest decision of the Apex Court in this regard
               rendered in case of S.V. Samudram v. State of Karnataka and Anr.2024 
               SCC Online SC 19. Paragraphs 62 to 73 are extracted here-under:      
                            62. Moving further, we now consider the judgment impugned before us, i.e.,
                            “                                                       
                            the order of the High Court upholding such modification, under the
                            jurisdiction of Section 37 of the A&C Act.              
                            63. It has been observed by this Court in MMTC Ltd. v. Vedanta Ltd.
                               As far as interference with an order made under Section 34, as per
                            “14.                                                    
                            Section 37, is concerned, it cannot be disputed that such interference under
                            Section 37 cannot travel beyond the restrictions laid down under Section 34.
                            In other words, the court cannot undertake an independent assessment of the
                            merits of the award, and must only ascertain that the exercise of power by the

                                            16  19                                  
                                         Page of                                    
                            court under Section 34 has not exceeded the scope of the provision. Thus, it is
                            evident that in case an arbitral award has been confirmed by the court under
                            Section 34 and by the court in an appeal under Section 37, this Court must be
                            extremely cautious and slow to disturb such concurrent findings.”
                                                              (Emphasis Supplied)   
                            64. This view has been referred to with approval by a bench of three learned
                            Judges in UHL Power Company Ltd v. State of Himachal Pradesh. In respect
                            of Section 37, this court observed:                     
                                                —                                   
                               As it is, the jurisdiction conferred on courts under Section 34 of the
                            “16.                                                    
                            Arbitration Act is fairly narrow, when it comes to the scope of an appeal
                            under Section 37 of the Arbitration Act, the jurisdiction of an appellate court
                            in examining an order, setting aside or refusing to set aside an award, is all
                            the more circumscribed                                  
                                          .”                                        
                            65. This Court has not lost sight of the fact that, as a consequence to our
                            discussion as aforesaid, holding that the judgment and order under Section
                            34 of the A&C Act does not stand judicial scrutiny, an independent
                            evaluation of the impugned judgment may not be required in view of the
                            holding referred to supra in MMTC Ltd. However, we proceed to examine the
                            same.                                                   
                            66. We may also notice that the circumscribed nature of the exercise of
                            power under Sections 34 and 37 i.e., interference with an arbitral award, is
                            clearly demonstrated by legislative intent. The Arbitration Act of 1940 had a
                            provision (Section 15) which allowed for a court to interfere in awards,
                            however, under the current legislation, that provision has been omitted.
                            67. The learned Single Judge, similar to the learned Civil Judge under
                            Section 34, appears to have not concerned themselves with the contours of
                            Section 37 of the A&C Act. The impugned judgment reads like a judgment
                            rendered by an appellate court, for whom re-examination of merits is open to
                            be taken as the course of action.                       
                            68. We find the Court to have held the award to be perverse and contrary to
                            public policy. The basis for such a finding being the delay on the part of the
                            contractor in completion of the work which “could have been avoided”.
                            Significantly, as we have observed earlier such a finding is not backed by any
                            material on record.                                     
                            69. What appears to have weighed with the court is that the factoring of the
                            cost escalation between the years 1989-1990 and 1992 by 100% was
                            exaggerated. But then equally, there is no justification in granting lump sum
                            escalation by 25% of the contract value. Well, this cannot be a reason to
                            modify the award for the parties are governed by the terms and conditions
                            and the price escalation stood justified by the petitioner based on cogent and

                                            17  19                                  
                                         Page of                                    
                            reliable material as was so counted by the Arbitrator in partly accepting
                            and/or rejecting the claims.                            
                            70. In our considered opinion, the court while confirming the modification of
                            the award committed the very same mistake which the Court under Section
                            34 of the A&C Act, made.                                
                            71. The Court under Section 37 had only three options:  
                                                             —                      
                              (a) Confirming the award of the Arbitrator;           
                             (b) Setting aside the award as modified under Section 34; and
                              (c) Rejecting the application(s) under Section 34 and 37.
                            72. The learned single Judge has examined the reasoning adopted by the
                            learned Arbitrator in respect of certain claims (claims 3 and 7, particularly)
                            and held that allowing a claim for escalation of cost, was without satisfactory
                            material having been placed on record and is “perverse and contrary to the
                                            it appears that such a holding on part of the Judge
                            public policy”. However,                                
                            is without giving reasons therefor. It has not been discussed as to what the
                            evidence was before the learned single Judge to arrive at such conclusion.
                            This is of course, entirely without reference to the scope delineated by
                            various judgments of this Court as also, the statutory scheme of the A & C
                            Act.                                                    
                            73. Having referred to J.G Engineers (P) Ltd. v. UOI and more particularly
                            para 27 thereof, it has been held that the award passed by the learned
                            Arbitrat                                                
                                 or is “patently illegal, unreasonable, contrary to public policy.”
                            There is no reason forthcoming as to how the holding of the learned
                            Arbitrator flies in the face of public policy.          
                                                      ”                             
               9.        In view of the aforesaid enunciation of law, there cannot be
               quarrel that the Arbitrator is the sole judge for construction of the terms and
               conditions of the agreement. But, what we find in the instant case, even
               learned Commercial Court has not made any reference to grounds of    
               challenge relating to price escalation and applicability of Clause 44 and 44.1
               of Agreement. Moreover, the Learned District Judge as well as the Sole
               Arbitrator has failed to consider whether the claimant-respondent is entitled
               to get payment relating to issue no.2 as the payment relating to issue no.2 has
               already been paid to contractor respondent.                          

                                            18  19                                  
                                         Page of                                    
               10.       The findings of the learned Commercial Court extracted     
               hereunder would unambiguously show that there has been complete non  
               consideration of any of the several grounds urged by the Appellant to
               question the impugned Award:                                         
                                           tioned facts, and judgments of Hon'ble Supreme
                         “Looking at the above men                                  
                    Court, this Court is of the opinion that the Arbitrator has legal authority to award
                    the pre-reference period interest, pendente lite interest and post award period
                    interest on the amounts which has been awarded in different heads of the Award.
                         The Applicant Executive Engineer, PWD(R&B), Kailashahar in his
                    application in his ground of challenge of award apart from challenging the award
                    relating to payment of interest, has also raised in dispute No 2 that payment for an
                    amount of Rs.1,20,425/- has also been made for 8276.651 cum @ 14.55 per cum
                    and as such claim as preferred by the claimant-contractor is not maintainable.
                    The applicant in his application has also in dispute Nos 3, 4, 5, 6, 7, 8 & 9 stated
                    above various items for which the claimant-contractor was not entitled to get, but
                    the Learned sole Arbitrator did not consider that. In my considered opinion, so far
                    as grounds of challenge of award relating to dispute Nos 3 to 9, are considered,
                    these are relating to re-examining and re-appraisal of the evidence considered by
                    the Arbitrator. It is also settled principle that award cannot be challenged on the
                    ground that Arbitrator has arrived wrong conclusion. The reasonableness of the
                    reason given by Arbitrator cannot be challenged. The Arbitrator is the sole Judge
                    of the quality of the evidence and it will not be for the Court to take upon itself the
                    task of being a Judge of the evidence before the Arbitrator. Moreover, scope of
                    interference by Courts in regard to arbitral award is limited. Courts do not sit in
                    appeal over the findings and decision of the Arbitration. Hence, the grounds of
                    challenge of award as stated by the applicant in his application as mentioned in
                    dispute Nos 3 to 9, cannot be considered and hence, accordingly rejected.
                         10. In the light of the aforesaid fact and circumstances, I am of the
                    considered view that the Learned sole Arbitrator has correctly passed the arbitral
                    award dated 17.06.2020 awarding penal interest in favour of respondent-
                    contractor and the same does not warrant for interference and it is not liable to be
                    set aside. This Court affirms the Award dated 17.06.2020.       
                                                          ”                         
               11.       The learned District Judge has failed to test the correctness of
               the award within the contours of the grounds available under Section 34(2)
               and 34(2-A) of the of the Arbitration and Conciliation Act, 1996 without

                                            19  19                                  
                                         Page of                                    
               referring to the relevant Clauses of the Agreement. Non-consideration of any
               of the grounds raised under Section 34 of the Act makes the judgment of the
               learned Commercial Court unreasoned and unsustainable.               
               12.       In view of the discussions made here-in-above, we are of the
               view that the matter be remitted to the learned District Court, Unakoti
               District to decide the grounds urged by the appellant and also as to the
               applicability of Clause 44 of the agreement and as regards to the expected
               loss of profit or adjustment in accordance with law within a reasonable time
               preferably 12(twelve) weeks from the date of receipt of the copy of this order
               since the Arbitration proceeding was initiated way back in the year 2019.
               Since the matter is remanded to the learned Commercial Court only on the
               grounds that the impugned Judgment shows complete non application of 
               mind and non consideration of the grounds urged in the Section 34    
               application, we have consciously refrained from observing any opinion on
               the grounds urged by the parties in the question of sustainability of the
               Award rewarded by the Arbitrator at this stage.                      
                         The appeal is disposed of in the manner and to the extent as
               indicated above.                                                     
               (ARINDAM   LODH,  J)           (APARESH   KUMAR   SINGH,  CJ)        
   Puspita / Rohit