2024:MLHC:682
Serial No. 05
Supplementary List
HIGH COURT OF MEGHALAYA
AT SHILLONG
WP(C) No. 196 of 2024
Date of Decision: 31.07.2024
M/s Hill Cements Company Ltd.,
…. Petitioner(s)
- Versus -
1. Meghalaya Power Distribution Company Ltd.,
Represented by its Chairman and Managing Director,
Lumjingshai, Shillong, Meghalaya.
2. Meghalaya Power Distribution Company Ltd.,
Represented by its Director,
Lumjingshai, Shillong, Meghalaya.
3. The Director (Distribution)
Meghalaya Power Distribution Company Ltd.,
Shillong, Meghalaya.
4. The Chief Engineer (Distribution)
Meghalaya Power Distribution Company Ltd.,
Shillong, Meghalaya.
5. The Executive Engineer, Khliehriat Distribution
Division, MePTCL, Khliehriat, Shillong
Meghalaya.
6. The Additional Chief Engineer, Eastern Zone,
MePDCL, Lumjingshai, Shillong, Meghalaya
7. The Assistant Executive Engineer,
Khliehriat Distribution Sub-Division,
Meghalaya Power Distribution Corporation Ltd.,
Ri-Bhoi.
8. The Superintending Engineer, (Adm.)
Lumjingshai, Shillong, Meghalaya.
… Respondent(s)
1 2
Page of
2024:MLHC:682
________________________________________________________
Coram:
Hon’ble Mr. Justice H. S. Thangkhiew, Judge
Appearance:
For the Petitioner(s) : Mr. K. Paul, Sr. Adv. with
Mr. S. Thapa, Adv.
For the Respondent(s) : Mr. A.S. Pandey, Adv. with
Ms. R. Colney, Adv.
i) Whether approved for reporting in Yes/No
Law journals etc.:
ii) Whether approved for publication
in press: Yes/No
ORAL
1. As there are some serious defects in the writ petition, Mr.
K. Paul, learned Senior counsel for the petitioner prays that he may be
allowed to withdraw the same with liberty to file afresh, if so advised.
2. Prayer is allowed, accordingly the matter stands closed on
withdrawal, with liberty as prayed.
JUDGE
Meghalaya
31.07.2024
“V. Lyndem-PS”
Signature Not Verified 2 2
Page of
Digitally signed by
VALENTINO LYNDEM
Date: 2024.07.31 16:41:14 IST