Skip to content
Order
  • Library
  • Features
  • About
  • Blog
  • Contact
Get started
Book a Demo

Order

At Order.law, we’re building India’s leading AI-powered legal research platform.Designed for solo lawyers, law firms, and corporate legal teams, Order helps you find relevant case law, analyze judgments, and draft with confidence faster and smarter.

Product

  • Features
  • Blog

Company

  • About
  • Contact

Legal

  • Privacy
  • Terms

Library

  • Acts
  • Judgments
© 2026 Order. All rights reserved.
  1. Home/
  2. Library/
  3. High Court Of Delhi/
  4. 2024/
  5. June

Union of India Through Executive Engineer vs. Ans Constructions Ltd

Decided on 28 June 2024• Citation: O.M.P. (COMM)/45/2019• High Court of Delhi
Download PDF

Read Judgment


                 *    IN THE  HIGH  COURT   OF  DELHI  AT  NEW  DELHI             
                                                  Reserved on: 15th February, 2024
                 %                               Pronounced on: 28th June, 2024   
                  +                  O.M.P. (COMM)  45/2019                       
                      UNION  OF INDIA  THROUGH   EXECUTIVE   ENGINEER             
                      Lucknow Central Division No. 2,                             
                              st                                                  
                      CPWD,  1 Floor, Kendriya Bhawan,                            
                      Section-H Aliganj, Lucknow, U.P.            ..... Petitioner
                                     Through:  Mr. Ruchir Mishra, Mr. Mukesh Kr.  
                                               Tiwari &  Ms. Reba Jena Mishra,    
                                               Advocates.                         
                                     versus                                       
                      ANS  CONSTRUCTION    LTD                                    
                      E-2/Block, B-1 Extension,                                   
                      Mohan Cooperative Industrial Estate,                        
                      Mathura Road, New Delhi-110044             ..... Respondent 
                                     Through:  Mr. Sushil Aggarwal, Advocate.     
                      CORAM:                                                      
                      HON'BLE   MS. JUSTICE NEENA  BANSAL   KRISHNA               
                                     J U D G M E N T                              
                 NEENA   BANSAL  KRISHNA,  J.                                     
                 1.   The  present Petition under Section 34 of the Arbitration and
                 Conciliation Act, 1996 (hereinafter referred to as the ) has been
                                                            “Act, 1996”           
                 filed on behalf of the petitioner for setting aside the impugned Award dated
                 20.08.2018 as corrected/clarified on 18.09.2018.                 
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                            Page 1 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                 2.   The petitioner/CPWD has sought to challenge the impugned Award
                 dated 20.08.2018 as corrected/clarified on 18.09.2018 on the ground that it
                 has been passed by ignoring the contractual provisions and applying the
                 extraneous provisions/conditions that were not part of the Agreement
                 between the parties.                                             
                 3.   The facts in brief are that the respondent/Claimant, a Private Limited
                 Company, was awarded Tender work for construction of various buildings at
                   th                                                             
                 20  Bn. Hqs. Balrampur.                                          
                 4.   An  Agreement bearing No. 48/EE/LCD-II/2010-11 (hereinafter 
                 referred to as the       ) was entered into between the parties for the
                               “Agreement”                                        
                 work  construction of Mahila Barrack, including internal electrical
                 installation to be constructed for Mahila Jawans of SSB Bn. Hqrs.,
                 Balrampur deployed for the national security along Indo-Nepal Border. As
                 per the terms of the Agreement, the date of start and date of completion of
                 work was stipulated as 06.03.2011 and 05.11.2011 respectively, but it got
                 completed on 07.10.2013, i.e. after about two years of stipulated date.
                 5.   The disputes arose inter se the parties after completion of work and a
                 list of 11 Claims was submitted by the /Claimant respondent to EE/LCD-II
                 vide Letter dated 05.12.2015. All the Claims were, after examination, held to
                 be not admissible and were rejected by the Executive Engineer vide Letter
                 dated 10.02.2016. The respondent filed an Appeal vide Letter dated
                 11.01.2016 under Clause 25(i) of the Agreement before SE/LCC. The SE
                 also after examining the same, came to the same conclusion that the Claims
                 were not permissible and rejected them all by his Letter dated 11.02.2016.
                 6.   Aggrieved by such rejection, the respondent filed an Appeal under
                 Section 25(i) of the Agreement before CE (NZ-II) along with the list of 11
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                            Page 2 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                 Claims on 17.02.2016. However, this Appeal also met the same fate of
                 rejection of all the Claims by CE (NZ-II) on 23.02.2016.         
                 7.   The respondent then gave a Notice of Invocation of Arbitration on
                 19.02.2016. The Arbitrator was appointed who eventually passed the
                 impugned Award dated 20.08.2018 as corrected/clarified on 18.09.2018.
                 8.   All the Claims were decided, but the petitioner is aggrieved by the
                 Claims No. 3, 5, 8 & 11 which are as under:                      
                    S. No. Claim     Claim                Amount Awarded          
                           Number                                                 
                       1.  Claim 3.  10CC (Price Escalation) Rs. 6,57,848         
                                     Claim for Civil materials                    
                                     component,    Labour                         
                                     Component &  Oil and                         
                                     Lubes component                              
                       2.  Claim 5.  Claim on  account of Rs. 11,31,239           
                                     Idling of Resources                          
                       3.  Claim 8.  Claim for extra cement Rs. 1,86,140          
                                     consumed in the project                      
                                     as recommended in the                        
                                     Design Mix and above                         
                                     the         minimum                          
                                     requirements                                 
                       4.  Claim 11. Claim  for  grant of 9%  per annum Simple    
                                     pendente lite and future interest on the award
                                     interest             awarded against Claim   
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                            Page 3 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                                                          No. 3, 4, 5, 6, 8 and 10
                                                          and  11%  per annum     
                                                          simple interest on the  
                                                          amount of the Award.    
                 9.   The petitioner aggrieved by the allowing of the Claims as mentioned
                 above, in favour of the respondent/ Claimant, has filed the present Petition
                 under Section 34 of the Act, 1996.                               
                 10.  The petitioner has submitted that there was a total delay of 702 days
                 in completion of the work. The Ld. Arbitrator attributed the delay of 109
                 days to the respondent and has accordingly imposed penalty, which has not
                 been challenged by the respondent. However, it has wrongly been observed
                 that the remaining 593 days of delay were attributable to the petitioner. It is
                 asserted that this understanding of the Arbitrator is incorrect because in
                 these 593 days of delay, the Arbitrator has included 337 days during which
                 the work could not progress due to the rain and the work site was inundated
                 with water.                                                      
                 11.  It is claimed that while awarding the Claim Nos. 3 and 5, the
                 Arbitrator has applied different yardstick to calculate the period of delay
                 attributable to the petitioner and the respondent respectively. While
                 observing that the Contractor cannot be held responsible for the delay in
                 completion of Work during the period of the rains, but this rain inundated
                 period of  337  days has  been added  to  the account of the     
                 petitioner/Department.                                           
                 12.  Further, the petitioner has submitted that the Contractor/respondent in
                 one of its Letter dated 27.06.2013 seeking extension of time, had stated in its
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                            Page 4 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                 own handwriting that he had not suffered any loss due to the delay in work
                 and that an extension be granted to complete the work for which it would
                 not raise any claim. Though this Letter was referred and relied upon by the
                 petitioner before the Ld. Arbitrator, but still compensation has been granted
                 on account of delay. The respondent/Claimant has taken a stand contrary to
                 its Letter in its Claim before the Arbitrator that it had suffered losses due to
                 delay in completion of work. This makes it evident that the Claims of the
                 respondent/Contractor are an afterthought and the same were liable to be
                 rejected in view of its own Undertaking in the Letter.           
                 13.  The petitioner has stated that the Claim No. 3 for escalation for civil
                 material component, labour component and oil lubes component, has been
                 allowed by the Ld. Arbitrator who has granted a sum of Rs. 6,57,848/- to the
                 respondent on the basis of Clause 10CC Formula, without appreciating that
                 this Clause which deals with price escalation and is not applicable to the
                 Agreement in question between the parties. The Arbitrator has ignored the
                 internal page 18 of the Contract wherein it was agreed by the parties that
                 Clause 10CC shall not apply to the present Contract as the stipulated period
                 of completion of work was less than 18 months under the Contract.
                 Therefore, the Award under Claim Nos. 3 for escalation and increase in
                 overhead expenses, by attributing a delay of 593 days to the petitioner, is
                 perverse and contrary to the material on record.                 
                 14.  It is further asserted that the judgments of M/s Nandsons Construction
                 Company  vs. MP State Tourism Development and Another, 2013 SCC  
                 OnLine MP  5294 and State of Orissa vs. Sudhakar Das (Dead) by LRs
                 (2000) 3 SCC have not been considered by the Arbitrator.         
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                            Page 5 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                 15.  In regard to Claim No. 5 which pertained to overhead expenses/ idling
                 of resources due to alleged prolongation of Contract, it is submitted that the
                 Ld. Arbitrator has ignored the contractual provisions and Undertaking of
                 the Contractor that he had not suffered any losses on account of delay in
                 completion of work and that he would not be making any Claim against the
                 petitioner-Department if the extension is granted. The respondent took
                 advantage of their Undertaking to get the extension but subsequently, it
                 reneged and raised a Claim against the petitioner on the ground of delay.
                 16.  It is further submitted that over calculation of overhead losses has
                 been done on the basis of Tender cost of Rs. 1,23,75,942/- instead of taking
                 actual completion cost of the work, which was Rs. 1,05,99,337/-. 
                 17.  The Arbitrator has calculated overhead expenses on account of idling
                 of resources by reducing them to the extent of 50% on the ground that the
                 workforce must have been deployed by the Contractor to do other work that
                 he had in the same premises/work site. Once the Ld. Arbitrator found it
                 reasonable to hold that the workforce of the Contractor was not sitting idle,
                 it was unreasonable and not justiciable for the Arbitrator to award even 50%
                 increase in overhead expenses, when there is a categorical finding of there
                 being no idling of resources of the respondent.                  
                 18.  Moreover, while attributing the delay of 593 days to the petitioner, the
                 Ld. Arbitrator has even included the period during which the workers were
                 not available during Diwali and Durga Puja and also the period during
                 which  they were  on strike because of their disputes with the   
                 respondent/Contractor. The days during which the workforce was not
                 available, have been erroneously included in 593 days which is a patent
                 illegality in the Award as the petitioner could not have been held liable to
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                            Page 6 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                 compensate the Contractor for delay on account of non-availability of
                 workforce, for the various reasons as mentioned above.           
                 19.  The petitioner has further submitted that under Claim No. 8 a sum of
                 Rs. 1,86,140/- on account of extra cement consumed in the Project as
                 recommended in Design Mix over and above the minimum requirements,
                 has been erroneously awarded to the respondent. It is claimed that the
                 Arbitrator had gone beyond his jurisdiction as there was an express
                 provision in the  Agreement  under Paragraph 8.8(iii) that the   
                 minimum/maximum  cement content for Design Mix concrete shall be 
                 maintained as per the quantity detailed therein even in case where the
                 quantity of cement required was higher than the minimum specified above,
                 to achieve the desired strength based on approved Mix Design and nothing
                 extra was to be paid. The Arbitrator has misinterpreted this express
                 provision and has allowed the Claim considering the order of preference
                 given in Paragraph 8.1 of General Condition of the Contract (GCC). It is
                 asserted that the Ld. Arbitrator has failed to appreciate that there was no
                 contradiction in the description of the item and condition mentioned under
                 Paragraph 8.8 (iii) of the Agreement.                            
                 20.  It is further contended that the party claiming compensation for any
                 loss of money has to prove such loss or damage suffered by him. In the
                 present case, the respondent miserably failed to provide any documentary
                 evidence as has also been observed by the ld. Arbitrator in Paragraph 45.0(i)
                 of the impugned Award. The Arbitrator has failed to appreciate that if a
                 party has not suffered any losses even if the breaches have been committed,
                 such party cannot be awarded any compensation under Section 73 & 74 of
                 the Indian Contract Act, 1872. By awarding the losses and damages, Section
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                            Page 7 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                 73 of the Indian Contract Act, 1872 has been rendered negatory and the
                 petitioner has been penalised despite there being no loss suffered by the
                 respondent.                                                      
                 21.  In the end, it is contended in respect of Claim No. 11 that an
                 exorbitant rate of interest @9% has been awarded which is untenable as the
                 Contractor/respondent got extension of time on the ground that he had
                 suffered no loss due to delay of work. No interest therefore, should have
                 been awarded to the respondent.                                  
                 22.  It is, therefore, submitted that the impugned Award dated 20.08.2018
                 as corrected/clarified on 18.09.2018, suffers from patent illegality and is
                 contrary to the express terms of the Contract. It is thus, liable to be set
                 aside.                                                           
                 23.  The respondent in its Reply to the Petition under Section 34 of the
                 Act, 1996 has denied all the grounds of challenge as agitated by the
                 petitioner in its present petition.                              
                 24.  While the facts are not in dispute, but it has been asserted that the
                 delay of 593 days has been rightly attributed to the petitioner. It is explained
                 that the respondent in its Letter dated 23.07.2013 seeking grant of extension
                 of time had nowhere stated that it has not suffered any losses on account of
                 delay or that it shall not claim any additional payment for the extension of
                 time. The respondent has further explained that it had filed its Claim No. 3
                 on account of price escalation on account of Delay which was based on
                 Clause 10CC as a tool for calculation or price escalation. The Arbitrator has
                 clearly observed that even though Clause 10CC was not applicable, it cannot
                 be denied that the P                                             
                                 roject was delayed primarily due to the petitioner‟s fault
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                            Page 8 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                 and failure to fulfil its reciprocal obligations. The respondent, therefore,
                 cannot be denied the legitimate compensation arising out of escalation in
                 price.                                                           
                 25.  Furthermore, the Arbitrator has observed that since the petitioner had
                 knowledge of serious probability and real danger of heavy rainfall and flood
                 at the Project site, still it did not warn the respondent which made it liable on
                 the doctrine of reasonable foreseeability. Reliance has been placed on the
                 decisions in Food Corporation of India vs. Am Ahmed & Co. and Ans., 13
                 SCC  779 and K.N. Sathyapalam vs. State of Kerala & Ans.¸ (2007) 13 SCC
                 43.                                                              
                 26.  The respondent has further submitted that it has accepted the delay of
                 109 days as attributed to it and the consequent penalty imposed upon it by
                 the Competent Authority. However, the balance delay of 593 days is not
                 attributable to the respondent. The work remained completely suspended as
                 the approved structural drawings were not provided by the petitioner and
                 further there were discrepancies in the drawings even on 05.03.2012 i.e.,
                 after one year of the day on which the Contract was awarded to the
                 respondent. The structural drawings for the first floor columns and slab,
                 including staircase and detailed drawings of toilets, doors and window
                 joinery were awaited on 05.03.2012. The Arbitrator while examining Claim
                 No. 3, has rightly imposed the penalty of Rs. 6,57,848/-, on the petitioner
                 and the challenge to it by the petitioner, is arbitrary.         
                 27.  The Arbitrator has rightly held that the petitioner has no moral basis
                 for insisting on documentary evidence of damages from the respondent.
                 Considering the principle of equity, fair play and justice, when the petitioner
                 had levied the penalty of Rs. 6,74,489/- as compensation for the alleged
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                            Page 9 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                 delay of 109 days on the part of the respondent, then the petitioner should
                 also correspondingly pay the damages suffered by the respondent for a
                 justified period of 593 days.                                    
                 28.  It is explained by the respondent that in case the formula of the
                 Petitioner is made applicable for                                
                                             the levy of compensation for 593 days‟
                 delay on the part of the petitioner, the respondent is entitled for Rs.
                 36,69,468/- (6,74,489 ÷ 109 days x 593 days) while the respondent has
                 merely been awarded Rs. 6,74,489/- as compensation. Hence, the Award is
                 fully justified and completely well-reasoned. The petition is liable to be
                 dismissed.                                                       
                 29.  In regard to Claim No. 5 which pertains to the Idling of resources, the
                 Ld. Arbitrator has calculated the element of overhead expenses for delayed
                 period which had been reduced by 50% for the reasons that the respondent
                 was having other works on the same site. The delay was purely attributable
                 to the petitioner because of which there was idling of machinery, etc. and the
                 amount of Rs. 11,31,239/- has been rightly awarded to the respondent.
                 30.  It is submitted that the Arbitrator has given a well-reasoned Award
                 which does not merit any interference.                           
                 31.  Learned Counsels for both the parties addressed their arguments in
                 detail and also submitted the Written Submissions.               
                 32.  Submissions heard and the record perused.                   
                 33.  At the outset it is pertinent to examine the scope of interference by
                 the Court in a Petition filed under Section 34 of the Act, 1996. 
                 34.  The scope of a challenge under Section 34 of the Arbitration and
                 Conciliation Act, 1996 is limited to the grounds stipulated in Section 34 as
                 held in MMTC Limited v. Vedanta Ltd, (2019) 4 SCC 163. Comprehensive
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                           Page 10 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                 judicial literature on the scope of interference on the ground of Public Policy
                 under Section 34 was postulated in Associate Builders v. DDA, (2015) 3
                 SCC  49. The Apex Court placed reliance on the judgment of ONGC v. Saw
                 Pipes, (2003) 5 SCC 705 to determine the contours of Public Policy wherein
                 an Award can be set aside if it is     The fundamental policy of 
                                             violative of „                       
                                                 Justice or morality              
                 Indian law‟, „The interest of India‟, „        ‟ or leads to a   
                  Patent Illegality .                                             
                 „             ‟                                                  
                 35.                               The fundamental policy of Indian
                      For an Award to be in line with the „                       
                     , the Tribunal should adopt a judicial approach which implies that the
                 law‟                                                             
                 Award must be fair reasonable and objective and in accordance with the law
                 of the land. The ground of patent illegality is applied when there is a
                                         „            ‟                           
                 contravention of the substantive law of India, the Act, 1996 or the Rules
                 applicable to the substance of the dispute.                      
                 36.  In Hindustan Zinc Limited v. Friends Coal Carbonisation, (2006) 4
                 SCC  445, the Apex Court referred to the principles laid down in Saw
                 Pipes (supra) and clarified that it is open to the court to consider whether an
                 Award is against the specific terms of the contract, and if so, it amounts to
                 patent illegality and is opposed to the Public Policy of India.  
                 37.  The  Apex  Court in  the case of Ssangyong Engineering &    
                 Construction Co. Ltd. v. NHAI, (2019) 15 SCC 131, has exhaustively dealt
                 with the expression patent illegality and which acts of the Arbitral
                                   “            ”                                 
                 Tribunal would come within the purview of patent illegality. The only
                 correct interpretation of a Contract would be if no reasonable person could
                 have arrived at a different conclusion while interpreting the relevant Clauses
                 of the Contract and that any other interpretation would be irrational and in
                 defiance of all logic. The findings would suffer from the vice of irrationality
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                           Page 11 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                 and perversity if the Arbitrator arrived at his findings by taking irrelevant
                 factors into account and by ignoring vital Clauses of the Contract. Hence,
                 the Apex Court held that the Court could intervene and review the merits of
                 an award if it is found to be on wrong interpretation of the Contract and
                 thus,             .                                              
                      „patently illegal‟                                          
                 Analysis and Findings:                                           
                 38.  Against this background, the question which arises for the  
                 consideration of this Court is: Whether the Award of the learned Arbitrator
                 warrants judicial interference on the grounds as narrated above? 
                 Delay in Completion of the Project:                              
                 39.  The foundational basis for the Claims No. 3 & 5 of the respondent,
                 was  the delay in completion of the contract. Admittedly, the date of
                 commencement and completion of the work, as per the Agreement dated
                 25.02.2011 was 06.03.2011 and 05.11.2011 respectively. It is further not in
                 dispute that the Contract got completed on 07.10.2013 i.e. after a delay of
                 702 days. The respondent had submitted its Claims essentially claiming the
                 increased amounts on account of delay in completion of the Project. The
                 petitioner had attributed the delay of 109 days to the respondent, which was
                 not challenged by the respondent. The Ld. Arbitrator also held delay of 337
                 days attributable to the petitioner while the remaining balance days of 256
                 was attributed to the rain and the work site being inundated with water. The
                 Ld. Arbitrator however, included the period of 256 days of rains in the delay
                 attributable to the Petitioner by observing as under:            
                      44. In this case I also find from the Extension of Time (EOT) case
                     “                                                            
                     Annexure R-30 of CSF  prepared the Respondent (Executive     
                     Engineer vide letter dated 28.02.2014) itself states that the
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                           Page 12 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                     stipulated date of start of the work and completion were 06.03.2011
                     & 05.11.2011 respectively. In the beginning of the work itself there
                     was a delay of 148 days i.e. from 06.03.2011 to 01.08.2011 due to
                     non-issue of good for construction structural drawings. Therefore it
                     would be seen that there was a clear delay of 5 months out of total
                     period of 8 months on  account of non-issue of Good for      
                     Construction structural drawings. After 01.08.2011 the work could
                     not be started due to inundation of entire work area on account of
                     rain water (cascading effect) and this delay continued upto  
                     24.10.2011. Therefore there was an initial delay of more than 7
                     months out of total stipulated period of 8 months for which  
                     Claimant was not responsible. This is a clear case that the  
                     Respondent committed fundamental breach of contract by not   
                     providing the site to the Claimant for execution of work due to non-
                     issue of structural drawings & inundation of the site during rainy
                     season initially for 7 months out of total 8 months period. No
                     breach of contract on the part of Claimant could be established by
                     the Respondent because according to Respondent itself the    
                     Claimant was responsible for a delay of 109 days out of total delay
                     of 702 days which took place in completion of work. Therefore the
                     Respondent is responsible to compensate for loss of damage to the
                     Claimant caused by breach of contract under section 73 of the
                     Indian Contract Act 1872.                                    
                                          ”                                       
                 40.  The learned Arbitrator in detail thus, considered the rival contentions
                 of the parties and referred to the Extension of Time (EOT) Letter dated
                 28.02.2014 prepared by the Executive Engineer/petitioner which stated that
                 in the beginning of the work itself, there was a delay of 148 days i.e. from
                 06.03.2011 to 01.08.2011 due to non-issue of good for construction
                 structural drawings. The learned Arbitrator while referring to this Letter
                 dated 28.02.2014 of the Executive Engineer, concluded that there was a
                 clear delay of 5 months out of the total period of 8 months of the Contract
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                           Page 13 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                 since 06.03.2011, on account of non-issue of the construction structural
                 drawings. Thereafter from 01.08.2011, the work could not be started due to
                 inundation of entire work area because of rain water. This delay in providing
                 the structural drawings had a cascading effect as the delay continued upto
                 24.10.2011, only when the work could be started.                 
                 41.  It was, therefore, held that the respondent could not be held
                 responsible for this delay of 7 months out of the stipulated period of 8
                 months. It was the petitioner who was held to have committed fundamental
                 breach of contract by non-issue of structural drawings, which led to further
                 delay on account of inundation of the site during the rainy season.
                 42.  This finding of the learned Arbitrator is challenged by the petitioner,
                 on the ground that the structural drawings were made available after 256
                 days, but the work could not be started in the following period apparently on
                 account of rains, for which the petitioner cannot be held responsible.
                 43.  It may be observed that the contract was for a period of 8 months and
                 it was well within the knowledge of both the parties that the latter part of the
                 Contract falls within the rainy season and the structural drawings ought to be
                 supplied in time for structural work to be completed before the onset of rains
                 and the structural work ought to be completed before the rains while the
                 other completion work would not have been hampered by rains. Since the
                 drawings were not supplied in time, the structural work could not be
                 commenced  during the rainy season leading to further delay. It has been
                 rightly observed by the learned Arbitrator that the delay in providing the
                 structural drawings had a cascading effect as the work could not be started
                 on account of rains. Had the structural drawings had been provided in time,
                 the work would not have been stalled from being commenced because of
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                           Page 14 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                 the rainy season, which led to a further delay in commencement of work on
                 account of rains leading to a delay of total period of 593 days, attributable
                 solely to the petitioner.                                        
                 44.  The learned Arbitrator has given reasons why the delay on account of
                 the rainy season though not the fault of the petitioner, but had to be
                 attributed to him because his initial delay further prevented the
                 commencement  of work in time on account of the rains. The learned
                 Arbitrator has rightly attributed the delay of 593 days to the petitioner.
                 There is no illegality in this finding and it does not merit any interference.
                 Findings on Claim No 3: Price escalation on account of the prolongation
                 of the Contract:                                                 
                 45.  Having concluded that the Ld. Arbitrator has rightly attributed the
                 delay of 593 days to the petitioner, the Claim No. 3 has to be considered
                 whereby the respondent has been allowed price escalation on account of the
                 prolongation of the contract.                                    
                 46.  The moot question before the Ld. Arbitrator was to ascertain the
                 principle for grant of the amount on account of prolongation of the Contract
                 due to delay. The learned Arbitrator accepted the plea of the petitioner that
                 Clause 10CC to determine the price escalation on account of prolongation of
                 the Contract, was not applicable to the present Case as the tenure of the
                 Project was less than 18 months. While acknowledging the non-applicability
                 of Clause 10CC, reference was made to the Case of Food Corporation of
                 India, (supra), wherein the Supreme Court had observed that      
                                                                 “Escalation, in  
                 our view, is normal and routine incident arising out of gap of time in this
                 inflationary age in performing any contract of any type. In this case, the
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                           Page 15 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                 arbitrator has found that there was escalation by way of statutory wage
                 revision and, therefore, he came to the conclusion that it was reasonable
                 allow escalation under the claim. Once it was found that the arbitration had
                 jurisdiction to find that there was delay in execution of the contract due to
                 the conduct of FCI, the corporation was liable for the consequences of the
                 delay, namely increase in statutory wages. Therefore, the arbitrator, in our
                 opinion had jurisdiction to go into this question. He has gone into that
                 question and has awarded as he did. The arbitrator by awarding wage
                 revision has not misconducted himself. The award was, therefore, made rule
                 of the high court, rightly so in our opinion.”                   
                 47.  Reliance has also been placed on K.N. Sathyapalam (supra) wherein
                 the Supreme Court considered the question of grant of Claim on account of
                 escalation of cost in the absence of a price escalation clause. It was
                 observed that                                                    
                             “Ordinarily, the parties would be bound by the terms agreed
                 upon in the contract, but in the event one of the parties to the contract is
                 unable to fulfil its obligations under the contract which has direct bearing
                 on the work to be executed by the other party, the arbitrator is vested with
                 the authority to compensate the second party for the extra costs incurred by
                 him as a result of the failure of the first party to live up to its obligations.
                 That is the distinguishing feature of cases of this nature and Alopi Parshad
                 case and also Patel Engg. case                                   
                                          .”                                      
                 48.  This principle was reiterated by the Apex Court in the Case of T.P.
                 George v. State of Kerala (2001) 2 SCC 758.                      
                 49.  The principles laid down in K.N. Sathyapalan (supra) were upheld by
                 the three Judge Bench of the Supreme Court of India in the Case of Assam
                 State Electricity Board & Ors. vs. Buildworth Private Ltd., (2017) 8 SCC
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                           Page 16 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                 146, wherein it was observed that                                
                                             “even though price escalation Clause in
                 the Agreement applied only to the specified period in the contract but it was
                 held to be applicable to the extended period because the parties through
                 their conduct permitted the belated performance of their reciprocal
                 obligations - Price escalation in performing any contract is a normal
                 incident                                                         
                        in this age of inflation.”                                
                 50.  After referring to the aforesaid judgments, the learned Arbitrator has
                 concluded that though Clause 10CC was not applicable in the facts of the
                 present case, but considering that the respondent/claimant was entitled to
                 price escalation on account of delayed performance of the Agreement, the
                 formula as provided in 10CC, can be adopted for ascertaining the price
                 escalation to which the respondent/claimant could be held entitled.
                 51.  It is quite evident that the learned Arbitrator has not held that Clause
                 10CC was applicable to the facts of the present case; rather it has been held
                 that the Clause 10CC was not applicable. Only the formula given in Clause
                 10CC, was adopted              since it is an established and widely
                                 by observing that “                              
                 accepted engineering method of working out the increase in the cost of work
                 due to delay in completion of work, as has also been held in the case of K.N.
                 Sathyapalan (supra) and also in the case of Food Corporation of India
                 (supra) and A.M. Ahmed Company (supra).                          
                                                   ”                              
                 52.  It had been observed that though Clause 10CC may not be applicable
                 but the                                                          
                       “assistance of this Clause, can be taken by the Tribunal, in working
                                                                          The     
                 out the increase in the cost of work due to various unavoidable delay.”
                 learned Arbitrator, therefore, has rightly invoked the principle/method as
                 contained in Clause 10CC for working out the price escalation due to
                 delayed completion of the Project.                               
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                           Page 17 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                 53.  The learned Arbitrator had also referred to the Judgment of M/s
                 Nandsons Construction Company (supra), wherein the Supreme Court 
                 relying upon the case of State of Orissa (supra), had held that  
                                                                       “in the    
                 absence of any escalation clause, an Arbitrator cannot assume any
                                                             In this case, the part
                 jurisdiction to award any amount toward escalation.”             
                 of the Award granting escalation charges, was held to be not sustainable as it
                 suffered from the patent illegality.                             
                 54.   This Judgment also observed that the fundamental principle of law is
                 that in the absence of Escalation Clause, no escalation charges can be
                 provided. The same principle has also been reiterated by the learned
                 Arbitrator who also has not held that Clause 10CC was applicable or
                 invoked Clause 10CC to grant the escalation cost, but has merely taken the
                 guidance of this Clause 10CC, to objectively ascertain the quantum of
                 compensation.. Therefore, this judgement also does not help the Petitioner in
                 any manner.                                                      
                 55.  Fundamentally, the finding of the learned Arbitrator is that because
                 there was a delay of 593 days attributable to the respondent, they are liable
                 to pay the escalation charges, which has been calculated on the basis of the
                 Formula contained in Clause 10CC only as an objective method of  
                 calculation of the escalation charges.                           
                 56.   This finding on Claim 3 is in accordance with law and does not
                 warrant any challenge.                                           
                 Findings on Claim No.5: on account of idling of resources.       
                 57.  The  petitioner has also challenged the grant of the sum of 
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                           Page 18 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                 Rs.11,31,239/- in Claim No.5 on account of idling of resources, to the
                 respondent.                                                      
                 58.  The learned Arbitrator while referring to the delay of 593 days
                 attributable to the respondent, also made a reference to the Letter of
                 Extension dated 23.07.2013, wherein while seeking Extension of Time, the
                 respondent had itself stated that it has not suffered any losses due to delay in
                 work. However, the learned Arbitrator granted the amount of Rs.  
                 11,31,239/-, while observing that when the penalty of Rs. 6,74,489/- has
                 been levied by the petitioner, on the respondent on account of delay of 109
                 days, the petitioner is also liable to pay the compensation in the same ratio
                 for being responsible for delay of 593 days. Consequently, the levy of
                 compensation on the petitioner, has been calculated on the prevalent
                 Engineering practices and in terms of the Agreement for calculating the
                 Contractors Profit (CP) and Overhead (OH).                       
                 59.  It has observed by the Ld. Arbitrator in paragraph 44 (ii) of the Award
                 the date of calculation of the compensation as under: -          
                       44(ii). It is widely accepted that also as per agreement that the
                      “                                                           
                                                          CP & OH) is 15% of      
                      element of overheads & contractor’s profit (                
                      the cost of the project. Out of 15%, 7.5% is the element of 
                      contractor’s profit and 7.5%, the element of overhead expenses.
                      The work was awarded to the Claimant by the Respondent vide 
                      letter dated 25.02.2011 (Exh. R-1 of CSF) for an amount of  
                      Rs.23,75,942/- and 8 months period was given for completion of
                      work. According to established principles of engineering practice
                      7.5% of the tendered cost i.e. Rs.9,28,196/- was the element of OH
                      (over heads) expenses which was included in the work. In other
                      words, the Claimant would have spent Rs.9,28,196/- on overhead
                      expenses if the work would have been completed by the Claimant
                      in 8 months. According to Respondent itself there was a delay of
                      593  days (19.5 months) for which the Claimant was not      
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                           Page 19 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                      responsible. Therefore, based on the above analogy the element
                      of overhead (OH) expenses in 19.5 months period work out to 
                      Rs.22,62,478/- as (Rs.9,28,196/- X 19.5 divided by 8). As the
                      claimant was having few other works in the Campus therefor the
                      overhead expenses will reduce. Considering this reduction in
                      overhead cost I reduce the overhead expenses by 50%. Therefore,
                      the net amount of damages suffered by the Claimant due to   
                      overhead expenses works out to Rs.11,31,239/-. I find that this
                      amount of Rs.11,31,239/- is reasonable & justified and the  
                      Claimant deserves to be compensated for alleged damages at least
                      up to this amount. I accordingly consider, decide & award   
                      Rs.11,31,239/- (Rs. Eleven lakhs thirty one thousand two hundred
                      thirty nine only) in favour                                 
                                           of Claimant against this claim.”       
                 60.  The law for grant of compensation is well settled that where a party is
                 unable to fulfil its reciprocal obligations as per the Contract, the claimant is
                 entitled to compensation due to damages/losses suffered as a consequence of
                 breach in terms of Sections 73 and 74 of the Indian Contract Act, 1872.
                 61.   In McDermott International Inc. vs. Burn Standard Company Ltd. &
                 Ors., (2006) 11 SCC 181, the Apex Court had observed that Sections 55 and
                 73 of the Indian Contract Act,1872 does not lay down the mode and manner
                 as to how and in what manner, the computation of damages or compensation
                 has to be made. As computation depends on circumstances and the methods
                 to compute damage how the quantum, therefore, should be determined, is a
                 matter which falls within the decision of the learned Arbitrator.
                 62.  The Apex Court in the Case of M/S Kailash Nath Associates v. DDA
                 and Anr. 2015 AIR SCW 759, held that if the party has not suffered any
                 losses even if the breaches have been committed by a party, such party
                 cannot be awarded any compensation under Section 73 of the Indian
                 Contract Act, 1872. The party claiming compensation, has to prove such
                 loss or damages as suffered by him. Until and unless, the damages or losses
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                           Page 20 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                 have actually been suffered, the same cannot be awarded under Section 73
                 of the Act. A party cannot be penalised even though the other party has
                 suffered no losses.                                              
                 63.  Coming to the facts of the present case, the respondent had claimed
                 damages suffered by it because of idling of resources in the extended period.
                 However, not only in his Letter of Extension dated 27.06.2013, has the
                 respondent stated that no losses shall be incurred due to delay in work and
                 would not seek any extra payments if the extension is granted, but it has also
                 been noted by the learned Arbitrator that there were five other Works of the
                 respondent which were on going on the same site at the given time. The
                 respondent admittedly has not led any evidence whatsoever to show the
                 losses that were suffered by it on account of idling of resources. In fact, the
                 observation of the learned Arbitrator that there were other Projects of the
                 respondent that were on going on the site further enures to the benefit of the
                 petitioner in so much as the circumstances do not justify any inference that
                 the losses on account of idling of machines, may have been suffered by the
                 respondent.                                                      
                 64.  It was the respondent who was claiming the compensation on account
                 of idling of resources. The onus was also on the respondent to prove by
                 some evidence about there being losses or extra charges suffered by the
                 respondent, on this account because of prolongation of the Contract. In the
                 case of Govt. of NCT of Delhi v. DSC Limited (2024 SCC OnLine Del 4147)
                 it was observed in Para 47 of the said judgment that in order to seek
                 compensation, it is required under Section 74 of the Contract Act to prove
                 that there is loss suffered. It reads as under:                  
                      47. In the end, it may be observed that the learned Arbitrator has
                     “                                                            
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                           Page 21 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                     rightly observed that the question of quantification of liquidated
                     damages would have arisen if it was established by the petitioner
                     that they had suffered some losses as is the requirement under
                     Section 55 and Section 74 of the Contract Act. There is not a
                     whisper about any losses having been suffered by the petitioner
                     during the intervening period of September 2010 till November
                     2011, which is a condition precedent for imposition of any   
                     liquidated damages.                                          
                                     ”                                            
                 65.  In the present case, no evidence whatsoever has been produced by the
                 respondent; rather its own Letter speaks to the contrary. When there is no
                 evidence whatsoever led by the respondent of there being any loss, then it
                 cannot be held entitled to any compensation in terms of Sections 73 and 74
                 of the Contract Act. Such has also been observed in the case of M/S Kailash
                 Nath Associates (supra), which is relied in the case of Edifice Developers
                 Project Engineers Ltd. v. Essar Projects (India) Ltd. (2013) 2 AIR Bom R
                 244 and also referred to in the case of Ajay Singh (Sunny Deol) v. Suneel
                 Darshan, 2015 SCC OnLine Bom 1412.                               
                     66.   It is, therefore, held that the grant of compensation on account
                 of idling of resources, is not only arbitrary but is also contrary to law and not
                 based on any evidence and is perverse. It suffers from patent illegality and
                 is, therefore, liable to be set-aside. The Apex Court in the case of Ssangyong
                 Engineering and Construction Company Limited v. National Highways
                 Authority of India (NHAI), AIR OnLine 2019 SC 329 in its Para 41 held
                 that a finding based on no evidence at all or an award which ignores vital
                    “                                                             
                 evidence in arriving at its decision would be perverse and liable to be set
                 aside on the ground of patent illegality and therefore, would also have to
                                                 …                                
                 be characterised as perverse.                                    
                                        ”                                         
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                           Page 22 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                 67.  Hence, if any finding is given without any evidence, it is perverse and
                 suffers from patent illegality. Therefore, the finding on Claim No.5
                 granting Compensation in the sum of Rs. 11,31,239 is held to be patently
                 illegal and is hereby set aside.                                 
                 Claim No. 8 for usage of extra cement:                           
                 The  petitioner has challenged the Claim No.  8, wherein  the    
                 respondent/claimant had made a Claim for extra cement consumed in the
                 Project as recommended in Design Mix over and above the minimum  
                 requirement in the sum of Rs. 3,61,121/-. It is asserted that Clause 8.1 of the
                 conditions of Contract, clearly stated that in the case of discrepancy between
                 the schedule of Quantities, the Specifications and/or the Drawings, the
                 following order of preference shall be observed: -               
                      “i). Description of Schedule of Quantities.                 
                      ii). Particular Specifications and Special Conditions, if any.
                      iii). Drawings.                                             
                      iv). CPWD Specifications.                                   
                      v). Indian Standard Specifications of B.I.S.”               
                 68.  As per the terms of Contract, the cement content was to be used in
                 RCC  Grade M-25 was 380 kgs, as per the Schedule of Quantities Item No.
                 3.4, however, Design Mix provided for consuming 450 kgs of cement per
                 cum  of RCC. The petitioner had asserted that in view of Clause 8.1 of
                 conditions of Contract, even though 450 kgs of cement per cum of RCC,
                 was used by the respondent but by virtue of Clause 8.1, it was entitled to
                 payment only @380 kgs of cement as minimum content.              
                 69.  The Ld. Arbitrator observed as under: -                     
                           (ii) According to the agreement when  there is a       
                      “55.0                                                       
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                           Page 23 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                      contradiction in the two clauses of the agreement then in that case
                      the issue is required to be decided according to order of   
                      preference given in para 8.1 of conditions of contract contained in
                      General Condition of Contract for Central PWD Works on page 
                      10 (Printed book) where it is specified that in the case of 
                      discrepancy between the schedule of quantities, the specifications
                      &/or  drawings the following order of preference shall be   
                      observed:-                                                  
                      i). Description of Schedule of Quantities.                  
                      ii). Particular Specifications and Special Conditions, if any.
                      iii). Drawings.                                             
                      iv). CPWD Specifications.                                   
                      v). Indian Standard Specifications of B.I.S.                
                      From the above para it is evident that nomenclature of item no.
                      3.4 of Bill of quantities will prevail over the clause 8.3 (iii) of the
                      „Additional Condition for RCC Work‟. Therefore as per this  
                      clarification the Claimant is entitled to get the payment of extra
                      cement consumed in M-25 mix of RCC. According to item no. 3.4
                      of Bill of quantities 380 kg of cement per cum of RCC was to be
                      considered while quoting the rate of RCC but as per Job Mix 
                      Formula 450 kg of cement per cum of RCC has actually been   
                      consumed. This is the admitted position of the Respondent also
                      that in M-25 grade of concrete the cement content @450 kg/per
                      cum of concrete has been actually used in the work. Therefore the
                      Claimant is entitled to get the payment of the cost of extra cement
                      i.e. 70 kg (450 kg 380 kg) consumed in excess in M-25 grade 
                                      –                                           
                      RCC  as compared to the quantity specified in agreement item no.
                      3.4 of Bill of quantities. The Claimant has provided the details in
                      Annexure 8 (pages 97, 98 & 99) attached with the Statement of
                      Facts (SoF). According to Annexure 8 (pages 97, 98 & 99)    
                      attached with Statement of Facts (SoF) total quantity of RCC (M-
                      25  grade) used in the work is 537.2 cum (281.81 cum in     
                      foundations and 255.39 in super structure) Rs.4,950/- per M.T. Is
                      the recovery rate of cement (PPC) specified in schedule „F‟ in the
                      table made  for recovery Rates for the quantities beyond    
                      permissible variation.”                                     
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                           Page 24 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                 70.  The  learned Arbitrator further observed that according to the
                 Agreement between the parties, when there was a contradiction in the two
                 Clauses of the Agreement, then the issue was required to be decided
                 according to the order of preference given in Paragraph 8.1 of Conditions of
                 Contract contained in General Conditions of Contract for Central PWD
                 Works. It was concluded that the nomenclature of Item No. 3.4 of Bill of
                 quantities, shall prevail over Clause 8.3(3) of the additional condition for
                 RCC  Work. Therefore, the respondent was held entitled to payment of extra
                 cement consumed in M-25 mix of RCC. It was the cost of excess cement and
                 was assessed at Rs.1,86,140/- in favour of the claimant.         
                 71.  From the aforesaid discussion, it is held that the findings given by the
                 learned Arbitrator for grant of the Claim for excess cement consumed in the
                 Project, is based on logic and reason. The findings do not suffer from any
                 patent illegality and do not call for any interference.          
                 Claim No. 11: for grant of pendente lite and future interest.    
                 72.  The  petitioner has also challenged the Claim No. 11 whereby
                 pendente lite interest @ 9% p.a. and simple interest @11% p.a. from the
                 date of award till the date of payment, has been awarded. The petitioner has
                 contended that the interest imposed is exorbitant.               
                 73.  The pendente lite and future interest as granted to the respondent on
                 the Award amount is in fact, much less than the interest rate on the
                 Commercial transaction. There is no basis for asserting that the interest rate
                 is exorbitant. This contention of the petitioner to challenge Claim No. 11 is
                 hereby rejected as not tenable.                                  
                 Partial Setting aside of the Award/ Claim:                       
                 74.  The conundrum which now arises is whether there can be partial
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                           Page 25 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                 setting aside of the Award or would it amount to modification of Award and
                 has to be necessarily set aside in toto leaving the parties for a fresh round of
                 arbitration, if so advised.                                      
                 75.  The said question had been engaging attention of the Courts and
                 divergent views have been taken by the Courts. The question came up for
                 consideration before Full Bench of Bombay High Court in the case of R.S.
                 Jiwani (M/S.) v. Ircon International Ltd., 2009 SCC OnLine Bom   
                 2021 wherein some claims were allowed while some were rejected. The
                 Bench observed as under:                                         
                                                                  to a party      
                     “36 …Could  there be a greater perversity of justice         
                     which has succeeded before the Arbitral Tribunal as well as in the
                     court of law but still does not get a relief. Is that what is
                     contemplated and was the purpose of introduction of the Act of
                     1996. An Act which was to provide expeditious effective resolution
                     of disputes free of court interference would merely become   
                     ineffective statute. Would not the canon of civil jurisprudence with
                     the very object of the Arbitration Act, 1996 stand undermined by
                     such an approach. The effective and expeditious disposal by  
                     recourse to the provisions of the 1996 Act would stand completely
                     frustrated if submissions of the respondent are accepted. Partial
                     challenge to an award is permissible then why not partial setting
                     aside of an award. In a given case, a party may be satisfied with
                     major part of the award but is still entitled to challenge a limited
                     part of the award. It is obligatory on the court to deal with such a
                     petition under section 34(1)(2) of the Act. We may further take an
                     example where the Arbitral Tribunal has allowed more than one
                     claim in favour of the claimant and one of such claim is barred by
                     time while all others are within time and can be lawfully allowed in
                     favour of the claimant. The court while examining the challenge to
                     the award could easily severe the time barred claim which is hit by
                     law of limitation. To say that it is mandatory for the court without
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                           Page 26 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                     exception to set aside an award as a whole and to restart the
                     arbitral proceeding all over again would be unjust, unfair,  
                     inequitable and would not in any way meet the ends of justice.
                                                                       ”          
                 76.  It was further observed that such an interpretation that the Award has
                 to be set aside in its entirety is bound to cause greater hardship,
                 inconvenience and even injustice to some extent to the parties. To compel
                 the parties, particularly a party who had succeeded to undergo the arbitral
                 process all over again does not appear to be in conformity with the scheme
                 of the Act. The provisions of Section 34 are quite pari materia to the
                 provisions of Article 34 of the Model Law except that the proviso and
                 explanation have been added to Section 34(2)(iv). The attempt under the
                 Model Law and the Indian Law appears to circumscribe the jurisdiction of
                 the court to set aside an award. There is nothing in the provisions of the Act
                 and for that matter absolutely nothing in the Model Law which can debar the
                 court from applying the principle of severability provided it is otherwise
                 called for in the facts and circumstances of the case and in accordance with
                 law. The courts will not get into the merits of the dispute. Thus, the
                 interpretation which should be accepted by the court should be the one
                 which will tilt in favour of the Model Laws, scheme of the Act and the
                 objects sought to be achieved by the Act of 1996.                
                 77.  In the case of R.S. Jiwani (supra), it was held that it is difficult to
                 prescribe legal panacea which, with regard to the applicability of the
                 principle of severability, can be applied uniformly to all cases. The judicial
                 discretion vested in the court in terms of the provisions of Section 34 of
                 the A&C Act, 1996 was held to take within its ambit, power to set aside an
                 award partly or wholly depending on the facts and circumstances of the
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                           Page 27 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                 given case and it was held that the same is not intended to be whittled down
                 or to divest the court of competent jurisdiction to apply the principle of
                 severability to the award of the Arbitral Tribunal, legality of which is
                 questioned before the court. Moreso, the proviso to Section 34(2)(a)(iv) has
                 to be read ejusdem generis to the main Section, as in cases falling in that
                 category, there would be an absolute duty on the court to invoke the
                 principle of severability where the matter submitted to arbitration can clearly
                 be separated from the matters not referred to arbitration and decision
                 thereupon by the Arbitral Tribunal.                              
                 78.  In the case of R.S. Jiwani (M/S.) (supra) a reference was made to the
                 decision of the Apex  Court of India in the case of NHAI v. M.   
                 Hakeem, (2021) 9 SCC 1 wherein it was observed that              
                                                              “Quite obviously if 
                 one were to include the power to modify an award in Section 34, one would
                 be crossing the Lakshman Rekha and doing what according to the justice of
                 a case, ought to be done. In interpreting a statutory provision, a Judge must
                 put himself in the shoes of Parliament and then ask whether Parliament
                 intended this result. Parliament very clearly intended that no power of
                 modification of an award exists in Section 34 of the Arbitration Act, 1996. It
                 is only for Parliament to amend the aforesaid provision in the light of the
                 experience of the courts in the working of the Arbitration Act, 1996, and
                 bring it in line with other legislations the world over.”        
                 79.  However, in R.S. Jiwani (M/S.) (supra) it was observed that the
                 observations were in regard to modification and not to the partial setting
                 aside of the Award. It was thus, concluded that the Court while exercising
                 power under Section 34 of the A&C Act, 1996, can set aside an Award
                 partly, depending upon the facts and circumstances of the case.  
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                           Page 28 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                 80.  In this context, reference was made to the judgment of the Supreme
                 Court in the case of J.G. Engineers Pvt. Ltd. v. Union of India, (2011) 5
                 SCC  758, wherein the doctrine of severability was invoked and it was held
                 that when the Award deals with several claims that can be said to be
                 separate and distinct, the Court can segregate the Award on items that do not
                 suffer from any infirmity and uphold the Award to that extent.   
                 81.  The Bombay High Court in the recent judgment of National Highway
                 Authority of India v. The Additional Commissioner, Nagpur, 2022 SCC
                 OnLine Bom 1688 noted the aspect of grave inconvenience highlighted in
                 the aforesaid Full Bench judgment of Bombay High Court in the case of R.S.
                 Jiwani (M/S.) (supra) and observed that if parties are required to go for
                 arbitration afresh in its entirety on every occasion, even when the arbitral
                 award is only partly set aside, that the arbitral award is found liable to be set
                 aside on some issues, it would lead to multiple rounds of litigation, going
                 against the very purpose of alternative dispute redressal mechanisms like
                 arbitration. The claimants would be forced to pursue numerous rounds of
                 proceedings before the arbitrator and Courts, which cannot be countenanced,
                 thereby indicating that the contention raised in this regard on behalf of the
                 appellants is unsustainable. Thus, following the principle of severability of
                 claims it was held that the Award may be set aside partially.    
                 82.   It is evident from the Claims 3, 5, 8 and 11 under challenge, that they
                 were all independent of each other and such part of the Award in respect of
                 Claim No. 5 which is independent, is liable to be set aside.     
                 Conclusion:                                                      
                 83.  The Petition under Section 34 Arbitration & Conciliation Act, 1996 is
                 therefore, partly allowed and the Award to the extent of Claim No. 5 in
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                           Page 29 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30                                                                      

                 regard to the grant of compensation in the sum of Rs.11,31,239/-, on
                 account of idling of resources, is hereby set aside.             
                 84.  The Petition under Section 34 is partly allowed.            
                                                   (NEENA  BANSAL  KRISHNA)       
                                                             JUDGE                
                 JUNE  28, 2024                                                   
                 S.Sharma/RS                                                      
    Signature Not Verified                                                        
    Digitally Signed O.M.P.(COMM) 45/2019                           Page 30 of 30 
    By:VIKAS ARORA                                                                
    Signing Date:12.07.2024                                                       
    16:11:30